Traditional contract: post occupancy evaluation
Post occupancy evaluation is the process determining how successful the delivery of the project was, how successful the completed development is, where there is potential for further improvement, and what lessons can be learned for future projects. It can be particularly valuable to repeat developers and may be a requirement of some funding bodies.
In practice, post occupancy evaluation may begin during the defects liability period, and ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointments and briefing documents can include a requirement to test whether objectives were achieved.
[edit] Appointing consultants.
Post occupancy evaluations may be carried out by an in-house team, by members of the consultant team or independent client advisers (we attribute them below to a consultant for simplicity of presentation). However, as post occupancy evaluation is likely to take place after the main construction contract has been completed, consultant team appointments may also be completed unless post occupation services were a specific requirement of the original appointments. If such services were not a requirement of the original appointments then new appointments may be necessary.
[edit] Carrying out a post project review.
A post project review may commence during the defects liability period. Its purpose is to evaluate the project delivery process rather than to assess performance in use (which is assessed later in this stage)
The consultant and client hold a start-up meeting to confirm the scope of evaluation required and agree the reporting procedures and programme for the stage. The client issues relevant information that may have been compiled during the design and construction phases to the consultant.
The consultant makes site visits to identify any issues that need to be addressed immediately. They may establish a help-desk and rapid response team if this has not already been done by the client.
The consultant monitors completion of the building owner's manual if this has not already been completed and ensures that other project documentation has been properly completed and handed over to the client (see handover to the client).
The consultant obtains the views of contractors, designers, suppliers and the client about how well the project was managed. This may include assessments of: the quality of briefing documents; the effectiveness of communications; the performance of the entire project team; quality issues; health and safety issues; certification; variations; claims disputes; and collaborative practices.
The consultant considers how well the delivery of the project performed against key performance indicators and evaluates what lessons can be learned from the approach taken. They then prepare an assessment and lessons learned report for the client.
[edit] Assessing performance in use.
Performance in use assessments cannot begin until 6 to 12 months after occupation, as operations may not be properly established and the building will not have operated in all seasons. It may then be part of a continuous process.
The consultant and client hold a start-up meeting to confirm the scope of the evaluation required and agree the reporting procedures and programme for the assessment. The client issues relevant information that may have been compiled to the consultant.
The consultant carries out evaluations of business objectives, which may include:
- The achievement of business case objectives.
- Whole-life costs and benefits against those forecast (including assessment of capital vs running costs).
- Whether the project continues to comply with the business strategy.
- Whether operations have improved.
- The resilience of the development and business to change.
- Business and user satisfaction (including staff and user retention and motivation).
The consultant carries out evaluations of the design, which may include:
- The effectiveness of the space planning.
- Aesthetic quality.
- The standards of lighting, acoustic environment, ventilation, temperature and humidity.
- Air-pollution and air quality.
- User comfort.
- Maintenance and occupancy costs.
- Defects.
- The balance between capital and running costs.
- An assessment of whether the development is being operated as designed.
- Environmental performance and energy consumption in use.
The consultant prepares a report that:
- Compares their findings to the original targets set out in business case (the original targets may need to be updated to reflect changes to the project brief during the design process, inflation etc).
- Compares findings to other projects and industry standards.
- Compares the outcome of the project with the position had the project not taken place.
- Identifies issues and recommends remedies.
- Makes recommendations for improvements in performance for future projects.
Other services that could be provided by consultants during this period might include: providing advice on letting, rating, maintenance, energy consumption, insurance, tenants queries, facilities management, the production of energy performance certificates, BREEAM assessments, the preparation of tender documents for maintenance and operation contracts and so on.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.