Types of risk in construction projects
Contents |
[edit] Risk
A risk is a potential event, either internal or external to a project, that, if it occurs, may cause the project to fail to meet one or more of its objectives.
Taking a risk involves a hazard combined with volition or will.
Even if a contract is silent on a particular risk, that risk will still lie with one party or the other. Wherever risk is shifted from one party to the other, there should be a counterbalancing change in price. Any discussion about whether or not a particular risk should be included in the price is a discussion of policy, not of ‘fairness’, ‘morality’ or ‘justice’.
Generally, risk is best allocated to the party best prepared for managing them.
[edit] Types of risk in construction projects
The first category of risk is often referred to as 'pure and particular risk'. It includes damage to persons and property (such as fire, storm, water, collapse, subsidence, vibration, etc.). Contract conditions often make it a contractual obligation to take out insurance cover against these risks.
The second category is 'fundamental risk'. This includes external factors such as: damage due to war, nuclear pollution, supersonic shock waves, government policy on taxes, labour, safety or other laws; malicious damage; and industrial disputes. Such incidents are all the subject of statutory liability and no insurance cover is normally available or needed.
The third category, often referred to as 'speculative risk', is something which can be apportioned in advance as agreed by the parties to the contract. This may include losses in time and money, which result from unexpected ground conditions, exceptionally adverse weather, unforeseeable shortages of labour or materials, and other similar matters beyond the control of the parties.
There are also risks of losses of time and money due to: delays and disputes (possession of site, late supply of information, inefficient execution of work, etc.); poor direction, supervision or communication; delays in payment; and delay in resolving disputes.
See Risk in building design and construction for more information.
See also:
- Commercial risks.
- Design risk.
- Excepted risk.
- Financial risks.
- Fire risk.
- Flood risk.
- Governance risks.
- Interface risk.
- Legal risks.
- Operational risks.
- People risks.
- Planning risk.
- Programme risks.
- Project risks.
- Property risks.
- Residual risk.
- Retained risk.
- Reputational risks.
- Security risks.
- Strategy risks.
- Systematic risk.
- Technology risks.
- Technological risk.
[edit] Common risks
Risk allocation and pricing approaches, guidance note, published by the Government Commercial Function in May 2021 identifies the following common risks:
- Data inaccuracy.
- Inflation.
- Performance/ availability.
- Volume/demand.
- Currency.
- Change in law.
- Solution/design risk.
- Delivery risk (Project delay).
- Scope change /specification.
- Supplier defaults.
- Termination.
- Subcontractor insolvency.
- Industrial action.
- Unforeseen events (force majeure).
[edit] Dealing with risk
- Identify the risk.
- Analyse the risk in terms of likely frequency of occurrence and severity of impact.
- Respond to the risk: make risks explicit so that decisions can be taken as to who should bear them.
[edit] Transfer of risk
- Contractual clauses are intended to transfer risks.
- When laying-off risks, weigh up the frequency of occurrence against the level of premium paid for the transfer.
- It can be unwise to pass a risk that is difficult to assess to the contractor as they may either increase their prices, or disregard it when preparing their bid and then find they are in difficulty later.
[edit] Acceptance of risk
- The client may carry highly unpredictable and poorly defined risks as the alternative might be to unacceptably inflate tenders.
[edit] Avoidance of risk
- Redefine the project.
- Clarification of responsibilities, remuneration, and expenditure at the beginning of the project to help avoid problems.
[edit] Insuring against risk
- Most standard form contracts insist on certain types of insurance, such as; insurance against fire, professional indemnity insurance, and so on.
[edit] Doing nothing about risk
- Either none of the project team considers the risk, or they consider the risk and decided that they already lie with those who could best control them.
[edit] Allocating risk through methods of payment
- Fixed price: items paid for based on the contractor’s predetermined estimate
- Cost reimbursement: items paid for based on what the contractor spends in executing the work.
[edit] Balance of risk for different forms of contract.
[edit] Design and build
There is a single point of responsibility with the contractor for both the design of the project and operations on site. As such, most of the risk lies with the contractor, particularly where the contract is let on a lump sum basis. However, risk is increasingly transferred back to the employer as more preparatory design work is carried out before the contract is let. It is important to agree who accepts the risk for obtaining permissions such as planning permission and building requlations approval.
[edit] Traditional contract
With traditional lump-sum contracts, the intention is that there should be a fair balance of risk between the parties. The employer is responsible for procuring the design and the contractor for undertaking the operations on site (although this is complicated when nominated sub-contractors and suppliers are included).
The balance can be adjusted as required, but the greater the risk assigned to the contractor, the higher the tender figure is likely to be. The risk to the employer is lessened by the contract being let on a lump-sum basis, although in reality, no price is 'fixed'. See fixed price contract for more information.
[edit] Management contracting
In management contracting the balance of risk lies with the employer. Separate works contracts are let, and the employer may continue to develop the design during construction, hence there may be little certainty about cost or time. However, the risk of delays and defects are associated with the responsibility for the works contracts. In some cases the management contractor may absorb this risk and with a resulting increase in price, although this may compromise their 'impartiality'.
[edit] Related articles on Designing Buildings
- Contingency plan.
- Crisis communications.
- Design risk management.
- Expected market cost.
- Principal-agent theory.
- Retained risk.
- Risk assessment.
- Risk in building design and construction.
- Risk management.
- Risk register.
- Commercial risks.
- Emergent risk.
- Financial risks.
- Governance risks.
- Legal risks.
- Non-technical risk.
- Operational risks.
- People risks.
- Programme risks.
- Project risks.
- Property risks.
- Reputational risks.
- Security risks.
- Strategy risks.
- Technology risks.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
Great article about the risks that may come up during a construction project. We actually included a link to it on our blog post about the importance of free construction software in the industry. Feel free to check it out
http://geniebelt.com/blog/why-our-industry-needs-free-construction-software
It would be nice if the following were included:
Performance bonds
When working in the ground
H&S and Environment (including designing out risks)
Picking your team to minimise risk