Residual risk in building development
The development of buildings is carried out in several phases, all involving hazard, uncertainty and risk. Risks which may occur on construction projects can sometimes be designed out or avoided. Remaining risks may be:
- Transferred to the contractor.
- Shared by the employer and contractor.
- Retained by the employer.
According to NRM2: Detailed measurement for building works, the term ‘residual risk’, or ‘retained risk’ refers to risks retained by the employer, that is, unexpected expenditure arising from risks that materialise, which are retained by the employer rather than being transferred to the contractor.
The employer may ask the contractor to provide a price for taking on a risk themselves before deciding to retain a risk.
Residual risks retained and managed by the employer or their project team are described as the employer’s residual risk exposure. Risk allowances should be included in cost plan to provide for this exposure.
Government Functional Standard, GovS 002: Project delivery; portfolio, programme and project management, Version: 2.0, published on 15 July 2021 by HM Government, defines a residual risk as: ‘The risk remaining after the risk response has been applied.’
[edit] Related articles on Designing Buildings
Featured articles and news
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.