Baseline schedule
Contents |
[edit] Introduction
Time management is one of the most important processes in project management. It is the discipline of planning and controlling the duration of a project. A baseline schedule is one of the main project management documents that should be created before the project starts. It sets out the project execution strategy, key project deliverables, activity planned dates and milestones.
Activities are grouped under different work breakdown structure levels. Engineering, procurement, production, testing, and so on are highlighted in baseline schedules.
[edit] Baseline schedule
A baseline schedule (also known as a schedule baseline or target schedule) is an approved copy of the project schedule that can be used to analyse project performance and report schedule variances. Baseline schedules create a road map to prepare the baseline budget, mobilisation plans, and resource allocation plans.
According to the Project Management Body of Knowledge (PMBOK) Guide, a Project Schedule represents 'the planned dates for performing activities and the planned dates for meeting milestones.'
Baselines are the frozen version of the project schedules. Before updating the project schedule for the first time, the baseline schedule is retained as a target. This means the baseline schedule is the same as the project schedule at the beginning.
As the project progresses and tasks are performed, the baseline schedule may deviate from the actual schedule. It may not reflect the current project status. Risks and unforeseen events may affect it, and some changes outside of the control of the project management team may cause delays.
Under these circumstances, remedial action should be taken and recovery plans created. It is important to emphasise that baselines should only be changed when there is a change in scope.
[edit] Baseline schedule tracking
After the approval of the baseline schedule by the stakeholders, it will be retained as a target. Schedule tracking is then carried out to analyse the differences between the planned and the actual dates. Changes in the critical path, schedule variances and delays are determined and reported in all updates.
[edit] Summary
In project time management, baseline schedules are used as references to analyse the schedule performance of the project. It is a reference document which compares the planned and the actual dates. A Schedule Performance Index (SPI) can be used to understand how far ahead or behind the project is at the point of analysis.
See also: Baseline programme.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Contractor's master programme.
- Contractor's working schedule.
- Design programme.
- How progress is agreed in construction.
- Milestones.
- Programme for building design and construction.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External resources
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.