Resource leveling
Resource leveling (or resource levelling) is a project management technique in which the demand for limited resources is accommodated by adjusting the project programme. In construction, resource leveling can be used to analyse the large variations in resource usage that can occur over time, and which can be inefficient and costly.
Speed of delivery may suggest that certain activities should be performed simultaneously. However, resources such as labour or plant may not be available in the quantities required, or may be occupied by a different activity. Practically therefore, activities may need to be scheduled sequentially, even though this may be slower.
Resource leveling can be used to determine when the project will be completed given the availability of resources.
In some situations, project scheduling may involve a combination of resource leveling and resource smoothing. Resource smoothing is an assessment technique used where the priority is the constraint on time rather than resources. It can be used to determine how best to complete the work by the required deadline, whilst minimising inefficiencies in resource demand.
Project management software can be used for resource leveling, which automatically calculates resource availability and potential delays and updates tasks accordingly. More complex software can be used to level resources company-wide, with the allocation of resources across multiple concurrent projects.
Common techniques that are used by project managers to assist with resource leveling, include:
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, defines resource levelling as: '...the process of amending a schedule to reduce the variation between maximum and minimum values of resource requirements. The process removes peaks, troughs and conflicts in resource demands by moving activities within their early and late dates and taking up float. Most project planning software offers an automated resource-levelling routine that will defer the performance of a task within the imposed logical constraints until the resources assigned to the tasks are available.'
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Critical path method CPM.
- Fast-track construction.
- Gantt chart.
- Line of balance (LOB).
- Milestones.
- Pareto analysis.
- Programme float.
- Project crashing.
- Resource allocation in design and construction.
- Resource management in construction.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
- Wiest-Levy method.
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.