Ponding water
In civil engineering, the term ‘ponding’ typically refers to the collection of standing water at the ground surface due to the presence of an impermeable layer within the soil. Ref The HS2 London-West Midlands Environmental Statement, Glossary of terms and list of abbreviations, DETR 2013.
It can also refer to the collection of water on an impermeable surface such as a roof, road or pavement where the fall is insufficient to allow surface water runoff, or where drainage is inadequate.
In extreme cases, ponding can be a sign of developing defect, such as settlement, structural movement or even the development of a sinkhole.
Typically ponding is considered to be an undesirable or unintended accumulation of water, unlike a water feature such as a pond, which is intentional. Ponding can cause damage, such as water penetration into buildings, defects on flat roofs and so on. However, it is typically less damaging that floods, which are generally larger in scale than ponding, which tends to be more shallow and localised.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.