Options appraisals for construction projects
Options appraisals are undertaken following the completion of feasibility studies. Their purpose is to assess a number of potential options before developing a concept design for the preferred option.
After assessing the feasibility studies, the client will decide which options the consultant team should develop. Ideally there will be no more than four options at this stage. If more options exist it may be necessary to carry out further high-level studies before proceeding to more detailed options appraisals.
Options appraisals might include diagrammatic options studies that enable the client to understand the broad pros and cons of the available options so that a preferred option can be selected.
These studies allow further assessments and discussions:
- An assessment of the risks of the options.
- Consultations with the local authority and other statutory authorities, to assesses possible planning permission requirements and other statutory requirements (such as the need for an environmental impact assessment for the options).
- Initial cost appraisals of the options.
Preparing appraisals may require further site surveys or site information. It may also be necessary to commission additional advice, such as planning advice, expertise on rights of light, engineering advice, or other specialist services depending on the complexity of the project. The need to commission other consultants will often be determined by the scale and location of a development and also by the client’s familiarity with the site and the local area. A large-scale development with underground constraints will almost certainly require engineering expertise in the early stages, whereas a residence in a traditional street may not. Both however may require an understanding of local authority or other statutory consultee positions.
The lead consultant can then co-ordinate the preparation of an options review report, from which the client can either select a preferred option or instruct the development of further options or appraisals.
The options review report might contain:
- A general description of the options.
- Diagrammatic sketch layouts.
- The overall consequences of each option for the client's operations.
- Assessment of compatibility with the clients vision, mission and objectives.
- Assessment of the overall feasibility of each option.
- Potential for future-proofing.
- Planning permission issues (including the potential requirement for an environmental impact assessment).
- Sustainability considerations.
- Impact on the local community and environment.
- Third-party dependencies.
- Value management exercises.
- Whole-life costs with a rudimentary assessment of costs/sqm, configuration and servicing.
- Time-frames, phasing and key milestones.
- Procurement route.
- Risks.
- Recommendations.
At this stage the client’s brief is likely to expand, partly from the conclusions of the appraisals but also from knowledge gained by research into planning precedents, legal issues, engineering data and the technical constraints and nature of the project.
Wherever possible, any information prepared or obtained should be in a format which can be readily shared and used, and should be stored and named in a way consistent with the long-term project and operational needs.
Once a preferred option has been selected, the consultant team may carry out further assessments to assist the client in preparing a business case and project execution plan for the preferred option before concept design begins.
[edit] Related articles
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.