OGC gateway review 4
The Office of Government Commerce (OGC) has now been absorbed into the Efficiency and Reform Group (ERG) within the Cabinet Office.
When it existed, the OGC produced a great deal of guidance about best practice in procurement and project management. This OGC guidance has now been archived, however, it is still cited in the new Government Construction Strategy and the revised Common Minimum Standards (to become the 'Construction Standards') and links are still provided from government websites such as the Major Projects Authority. The OGC gateway review process still provides one of the best and most comprehensive sets of guidance for public projects. It is for this reason that the project plan for public projects within Designing Buildings Wiki follows the OGC gateway review process. See Public project: outline work plan.
The procurement routes preferred by the Government Construction Strategy and described by the OGC gateway review process are private finance initiative (PFI), prime contracting and design and build (see OGC Achieving Excellence Guide 6:Procurement and contract strategies). The Government Construction Strategy states that traditional procurement routes that separate design from construction should not be used unless it can be demonstrated that they offer better value for money.
The three preferred routes involve appointing a single integrated supply team (including designers, contractors, suppliers and perhaps facilities managers) after the project brief has been prepared, before design commences. This means that the main decision to invest (i.e. to appoint the integrated supply team), takes place before any designs have been prepared.
The OGC Gateway Review process offers a structure for projects following these procurement routes, based around a series of independent peer reviews carried out at key stages to verify that projects should be allowed to progress to the next stage.
These peer reviews, or 'gateway reviews' are commissioned on a confidential basis by the Senior Responsible Owner:
- OGC gateway review 0: strategic assessment.
- OGC gateway review 1: business justification
- OGC gateway review 2: delivery strategy (or procurement strategy)
- OGC gateway review 3: investment decision
- OGC gateway review 4: readiness for service
- OGC gateway review 5: operations review & benefits realisation (or benefits evaluation)
There are also two additional decision points specific to building projects:
In practice, some of the design work leading up to these decision points is likely to be carried out during the tender process (or bidding process on PFI projects).
OGC state that the purpose of gateway review 4: readiness for service is to:
- Check that the current phase of the contract is properly completed and documentation completed.
- Ensure that the contractual arrangements are up-to-date.
- Check that the Business Case is still valid and unaffected by internal and external events or changes.
- Check that the original projected business benefit is likely to be achieved.
- Ensure that there are processes and procedures to ensure long-term success of the project.
- Confirm that all necessary testing is done (e.g. commissioning of buildings, business integration and user acceptance testing) to the client’s satisfaction and that the client is ready to approve implementation.
- Check that there are feasible and tested business contingency, continuity and/or reversion arrangements.
- Ensure that all ongoing risks and issues are being managed effectively and do not threaten implementation.
- Evaluate the risk of proceeding with the implementation where there are any unresolved issues.
- Confirm the business has the necessary resources and that it is ready to implement the services and the business change.
- Confirm that the client and supplier implementation plans are still achievable.
- Confirm that there are management and organisational controls to manage the project through implementation and operation.
- Confirm that contract management arrangements are in place to manage the operational phase of the contract.
- Confirm arrangements for handover of the project from the SRO to the operational business owner.
- Confirm that all parties have agreed plans for training, communication, rollout, production release and support as required.
- Confirm that all parties have agreed plans for managing risk.
- Confirm that there are client-side plans for managing the working relationship, with reporting arrangements at appropriate levels in the organisation, reciprocated on the supplier side.
- Confirm information assurance accreditation/certification.
- Confirm that defects or incomplete works are identified and recorded.
- Check that lessons for future projects are identified and recorded.
- Evaluation of actions taken to implement recommendations made in any earlier assessment of deliverability.
Ref OGC gateway process review 4: readiness for service.
According to OGC, the tasks that should be undertaken prior to gateway review 4: 'readiness for service' should include:
- Construction begins.
- Ongoing regular review by IPT (integrated project team) senior management to address major issues arising.
- Monitor and report on progress against contract programme; issue monthly project progress reports.
- Check work against specification; test materials. Ensure implementation of quality assurance system.
- Manage expenditure of risk allowance; maintain latest estimated cost and cash flow; initiate action to avoid overspend; issue monthly financial status reports; submit high level reports to senior management.
- Ensure payments are made in line with contractual arrangements. Note: for PFI (private finance initiative) and PDS (Private Developer Scheme) projects, payment does not begin until facility is ready for use.
- If required, use alternative dispute resolution procedures agreed in partnering charter to resolve disputes. See OGC guidance on alternative dispute resolution.
- Maintain records of site activities; daily diary; site instructions; inspection and test results.
- Establish commissioning team; carry out commissioning programme at the earliest opportunity in the construction phase and during the course of the work, rather than just before handover; check programme and coordinate with overall programme; confirm/witness commissioning. Prepare for handover and operation, including 'decant' as appropriate.
- Check quality of work, defects, completeness and performance. Record results; and fix any defects.
- Ensure that all specified deliverables (such as operating and maintenance manuals, health and safety file) are delivered by IPT (integrated project team) and fit for purpose.
- Issue certificates required on completion.
- Review the acceptability of the completed project. Aim to agree final account as close completion as possible. Handover to client (unless ongoing management of facility under contract).
- Confirm that construction is complete in accordance with the contract. Confirm that the facility is ready for service; confirm the client's readiness to take on the facility.
ref OGC: Achieving Excellence Guide 3 - Project Procurement Lifecycle P14.
For a detailed description of the sequence of tasks necessary on public projects, see the free work plan available from Designing Buildings Wiki: Public project: outline work plan. Gateway review 4 takes place at the end of the work stage: Public project: construction. This is because OGC state that... .
..for property/construction projects, this Review takes place after the project has been approved as ready for use. Commissioning will have taken place, although this will not be completed until after occupation, as systems are re-balanced to take account of the effect of occupancy.
ref OGC Gateway™ Process Review 4: Readiness for service P8.
[edit] Related articles on Designing Buildings Wiki
- Design and build.
- Gateway.
- Government Construction Strategy.
- OGC.
- Output based specification.
- Private Finance Initiative.
- Prime contract.
- Public procurement.
- Major Projects Authority.
[edit] External references
Featured articles and news
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA has launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments