Non payment in the construction industry
Contents |
[edit] Introduction
Non-payment in construction can also be referred to as withholding payment. This can be due to a dispute or contractual breach between two parties for non-performance of a certain clause. Provided that a party to a contract issues a compliant withholding-notice setting out the grounds and the sums attributable to each ground, then the party may legitimately withhold payment.
In this respect, the provisions set out in the Housing Grants, Construction and Regeneration Act and the Scheme for Construction Contracts will take precedence over any client payment clauses and will need to be adhered to.
[edit] The Housing Act guidelines to adhere to prior to withholding payment
Payment in construction is be subject to the Housing Grants, Construction and Regeneration Act 1996 (also known as the Construction Act). This provides for:
- The right to be paid in interim, periodic or stage payments.
- The right to suspend (or part suspend) performance for non-payment and to claim costs and expenses incurred and extension of time resulting from the suspension.
- The right to be informed of the amount due, or any amounts to be withheld.
- Disallowing pay when paid clauses.
The client must issue a payment notice within five days of the date for payment, even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice.
The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation. The notified sum is payable by the final date for payment.
If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a pay less notice, they must pay the amount in the default payment notice.
The Late Payment of Commercial Debts Regulations also imposes a limit of not more than 30 calendar days (before the payment period begins) for a purchaser to verify the conformity of goods/services are in accordance with the contract - but this period can be exceeded by agreement and provided it is not grossly unfair to the supplier.
[edit] Grounds for non payment
To withhold payment the following grounds must be met as a minimum:
- The notice to withhold must be compliant with the contractual requirements.
- The notice to withhold must be compliant with the means of issue (e.g. recorded delivery post).
- The cause (breach) of the contract giving entitlement to withhold must be stated. It is important to set out the grounds and the amount attributable to each ground.
- A loss must naturally flow from that breach.
- The valuation of the payment withheld must be prepared correctly.
[edit] JCT and NEC compared
There are significant differences in the timescales for withholding payment in JCT and NEC Contracts. Each contract sets out their own payment due dates. As a general guide, the JCT stipulates that a withholding notice will need to be issued at least 5 days in advance of the final date for payment. The NEC has a longer period of 7 days. These dates however will be specific to each contract and will have to be adhered to for a valid non-payment/withholding-notice to be issued.
If the provisions of a contract do not comply with the Housing Grants, Construction and Regeneration Act, then the Scheme for Construction Contracts will apply.
[edit] Conclusion
The non-payment/withholding-notice in construction has to meet several legislative and contractual points to be valid. Contractors are within their rights to suspend performance for non-payment so due diligence will need to be carried out by both parties to avoid disputes and disruption to the construction project.
For more information see: Late payment.
[edit] Related articles on Designing Buildings Wiki
- Causes of construction disputes.
- Fair payment practices.
- Housing Grants, Construction and Regeneration Act.
- The Late Payment of Commercial Debts Regulations 2013.
- Payment notice.
- Payments to nominated sub-contractors.
- Pay less notice.
- Payment.
- Payment schedule.
- Prompt payment code.
- The causes of late payment in construction.
Featured articles and news
Construction industry reactions to the election result
ECA, CIAT and more to come as published.
At a Crossroads; Pathways to a Net Zero Future
Background to and summary of this key Renewable UK report.
Installing solar panels on listed structures.
The current and future global market dynamics of boilers
Significant challenges but adaptation to sustain for longer.
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.