Non-performance in the construction industry
Non-performance is a general term that describes a party which fails to perform; in fact, the term can cover all forms of failure in performance. A student who fails end-of-year exams may be regarded by the school as a non-performer. In this respect, non-performance is not contractually linked – the student never promised to do well and there was no contact entered into, written or otherwise.
In simple terms, a contract is a legally-binding promise. From a legal perspective, the basis of every contract is that all parties must fulfil all of the contract's terms. Non-performance occurs when one party to the contract does not fulfil the contract terms – failing to live up to their contractual obligations. Such a failure is not necessarily a breach of contract although it could lead to a breach of contract.
A breach of contract in English Law is non-performance that is not excused because it is the non-performance of a contractual obligation, i.e. a promise was made and was not kept. A breach of contract entitles the innocent party to receive damages from the guilty party. It may also allow the innocent party the right to terminate the contract.
An example of non-performance is a contractor who fails to provide sufficient labour, materials or equipment to a project, leading to a delay to the completion date.
Bonds can provide a degree of protection for the client. Bonds are an undertaking by a bondsman or surety to make a payment in the event of non-performance. Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence of the contractor's non-performance, and that as a consequence the client has suffered a loss.
[edit] Refusal to perform or declaration of non-performance
A declaration of non-performance is another form of non-performance. One party declares they are abandoning any further performance under the contract or refuses to fulfil an essential aspect of the contract. In this case, the innocent party can discharge themselves from any further performance obligations.
[edit] Related articles on Designing Buildings Wiki
- Bonds in construction contracts.
- Construction contract conditions
- Contractual obligation.
- Contractual right.
- Delay analysis.
- JCT
- JCT Construction management contract
- Performance bond
- Procurement team
- Standard form of contract
- Tender documentation for construction projects
- Traditional contract for construction
- Traditional contract: tender
- Typical tender process for construction projects
Featured articles and news
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Key points and relevance to construction of meeting, due to reconvene.