New Engineering Contract
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
The intentions of NEC contracts include:
- Stimulating good management.
- Being clear and simple, written in plain English, in the present tense and without legal terminology.
- Being useable in wide variety of situations from minor works to major projects
The suite of documents now include:
- NEC4: Alliance Contract
- NEC4: Design Build and Operate Contract
- NEC4: Dispute Resolution Service Contract
- NEC4: Engineering and Construction Contract
- NEC4: Engineering and Construction Short Contract
- NEC4: Engineering and Construction Short Subcontract
- NEC4: Facilities Management Contract
- NEC4: Facilities Management Short Contract
- NEC4: Facilities Management Short Subcontract
- NEC4: Facilities Management Subcontract
- NEC4: Framework Contract
- NEC4: Professional Service Contract
- NEC4: Professional Service Short Contract
- NEC4: Professional Service Subcontract
- NEC4: Supply Contract
- NEC4: Supply Short Contract
- NEC4: Term Service Contract
- NEC4: Term Service Short Contract
- NEC4: Term Service Subcontract
The Engineering and Construction Contract has 6 options:
- NEC4: Engineering and Construction Contract Option A priced contract with activity schedule
- NEC4: Engineering and Construction Contract Option B: priced contract with bill of quantities
- NEC4: Engineering and Construction Contract Option C: target contract with activity schedule
- NEC4: Engineering and Construction Contract Option D: target contract with bill of quantities
- NEC4: Engineering and Construction Contract Option E: cost reimbursable contract
- NEC4: Engineering and Construction Contract Option F: management contract
There are a number of articles relating to NEC on Designing Buildings:
- Accepted programme.
- Activity schedule
- Compensation event.
- Cost reimbursable contract.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early contractor involvement.
- Early warning notice.
- Key dates.
- Latham Report.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC contracts and collaborative working.
- NEC early contractor involvement.
- NEC early warning notices - a tool of mutual benefit.
- NEC3.
- NEC4.
- NEC Option A: Priced contract with activity schedule.
- NEC Option B: Priced contract with bill of quantities.
- NEC Option C: Target contract with activity schedule.
- NEC Option D: Target contract with bill of quantities.
- NEC Option E: Cost reimbursable contract.
- Period for reply.
- Term Contract.
- The NEC and the Z clause.
- Time Risk Allowance.
- Z clauses.
[edit] Related articles on Designing Buildings
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.