London Power Tunnels
Contents |
[edit] Introduction
The London Power Tunnels project is a National Grid infrastructure investment in London’s electricity transmission system. The project is the first significant renovation of the city’s power grid since the 1960s. The total cost is estimated at £1bn and is expected to take 18 years.
Much of London’s electricity infrastructure is already delivered through a network of underground cables. However, the majority of this network is just below the surface of the road, which means maintenance (and any significant replacement) takes place above ground - causing significant disruption to the city’s traffic. The construction of new tunnels requiring a significant amount of excavation under Tube lines, canals and rivers provides an alternative.
[edit] Section One
The first phase of the project, known as LPT1, began in February 2011 and was completed in 2018.
This phase concentrated on constructing a 30km network of underground tunnels from Hackney to Willesdon from east to west, and from Kensal Green to Wimbledon in the south. The works required the installation of the longest single-length power cables in an underground utility tunnel in the country.
The tunnels carry 192km of 400kV cable and 30km of 132kV cable. This created 10 new transmission circuits which are able to support 20% of London’s electricity demand.
To support National Grid’s sustainability initiatives, the organisation recycled 99% of the materials excavated during this phase of the project.
[edit] Section Two
Referred to as London Power Tunnels (LPT2), the second phase of the project began in March 2020. This will carry a network of cable tunnels from Wimbledon to Crayford. It is projected that LPT2 will be fully operational by 2026.
The majority of LPT2 tunnels will be approximately 30m deep. This is roughly equivalent to the height of a 10 storey building. This second phase will result in a new network of cable tunnels approximately 32.5km in length.
[edit] Related articles on Designing Buildings
Featured articles and news
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.