Gateway Arch
Contents |
[edit] Introduction
The Gateway Arch is a structural expressionist monument located on the west bank of the Mississippi River in St. Louis, Missouri. It was built as a monument to the westward expansion of the United States. At 192 m (630 ft) in height, it is the world’s tallest arch, and the tallest man-made monument in the Western Hemisphere.
The idea was conceived as part of the Jefferson National Expansion Memorial (JNEM), created in 1935. A nationwide design competition was held in 1947/48 and Ero Saarinen’s arch was chosen as the winner. Since its completion in 1965, it has become a popular tourist attraction and a defining symbol of the city of St. Louis.
[edit] Design
Eero Saarinen conceived of the monument as being clad in stainless steel and built in the form of an inverted, weighted catenary arch, a shape such as would be formed by a heavy chain hanging freely between two supports.
The arch spans 192 m (630 ft) between the outer faces of its triangular legs. Each leg is an equilateral triangle, narrowing from 16 m (54 ft) per side at the bases to 5.2 m (17 ft) at the top. Complex mathematical equations were required to ensure the arch design would work, and the base of each leg at ground level had an engineering tolerance of just 0.4 mm (1/64 inch) to ensure they would meet at the top.
Each leg consists of a stainless steel skin covering two carbon-steel walls with reinforced concrete sandwiched between them. This continues until 91 m (300 ft), at which point carbon steel stiffeners are used instead of concrete. These inner and outer stressed-skins join to form a composite structure which carries the self weight and wind loads to the ground.
Each leg is embedded in concrete foundations 13 m (44 ft) thick and 18 m (60 ft) deep. The arch is earthquake-resistant and designed to sway up to 46 cm (18 inches) in either direction, while withstanding winds of up to 150 miles per hour.
The arch is hollow and accommodates a tram system that carries visitors from the lobby to an observation deck at the top. Operating at the rate of 340 ft per minute, the ride takes 10 minutes for the full trip. The observation platform is 65 x 7 ft, and fitted with plate-glass windows that provide views to the east and west.
[edit] Construction
Construction was postponed during World War II, and it wasn’t until 1959 that ground was first broken. The foundations were laid in 1961, and the arch construction itself began in 1963 as the first steel triangle for the south leg was moved into place.
The steel triangles, narrowing as they spiralled to the top, were raised into place using a group of cranes and derricks. Once in place, each section was filled with concrete and prestressed with 252 tension bars. As a means of keeping the partially-completed legs steady, a scissors truss was placed between them at 160 m (530 ft). This was later removed as the derricks were dismantled.
Construction progress was delayed by a combination of funding issues, safety checks and legal disputes. Civil rights activists brought work to a stand-still as strikes were held in protest against the fact that African-American workers, who were being discriminated against, were working on the project.
On October 28 1965, the arch was finally topped out. The keystone was a 2.4 m (8 ft) long triangular section. To mitigate against thermal expansion, which had constricted the gap at the top by 13 cm (5 inches), fire hoses were used to spray water to cool the surface and help it contract. When the keystone was in place, a hydraulic jack was used to pry the legs apart 1.8 m (6 ft), with the final section being inserted to secure the arch.
Having cost $13 million (equivalent to $190 m in 2015), the arch opened to the public in June 1967.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.