Fit out of buildings
Contents |
[edit] Introduction
‘Fit out’ is a term used to describe the process of making interior spaces suitable for occupation. It is often used in relation to office developments, where the base construction is completed by the developer, and the final fit out by the occupant. The occupant will generally be leasing space as a tenant from the developer/landlord.
Approved document L of the building regulations defines fit out as:
...that Work needed to complete the internal layout and servicing of the building shell to meet the specific needs of an incoming occupier. The building shell is the structural and non-structural envelope of a building provided as a primary stage (usually for a speculative developer) for a subsequent project to fit out with internal accommodation works. |
Depending on the degree of completion of the building, and the interior specification required by the occupant, fit outs can take a range of different forms:
[edit] Shell and core
Shell and core works will generally comprise the structure, cladding, base plant, completed common areas and external works. It will include fitted-out main reception, lobbies, staircases, toilets, lift shafts, basements, loading bays, car parking, and so on.
[edit] Category A fit-out
Category A (Cat A) generally describes the level of fit out that the tenant's own space is completed to by the developer. There is no standard definition, but a category A fit out may include.
- Raised floors and suspended ceilings.
- Distribution of mechanical and electrical services.
- Internal surface finishes.
- Blinds.
If the tenant has very complex fit out requirements, this may impact on the category A fit out. In this case, they may make a contribution to the costs of the category A fit out to ensure that it meets their needs, and offset this against their own costs. This saves wasted time and money modifying the category A fit out.
For more information see: Category A works.
[edit] Category B fit-out
Category B (Cat B) completes the fit out of the internal space to the tenant's requirements. This may include:
- Final finishes and branding.
- Installation of offices.
- Installation of specialist facilities in meeting rooms, board rooms conference rooms, and so on.
- Fitting out reception areas.
- Installation of specialist lighting.
- Installation of ICT equipment.
- Installation of audio visual equipment.
- Fit out of kitchen areas.
- Installation of furniture.
The developer may make ask the tenant to carry out some of their more sensitive category A works on their behalf during the category B fit out, when they may be less subject to damage. The developer will pay the tenant a sum equivalent to the cost of the works had they carried them out themselves.
For more information see: Category B works.
[edit] Turnkey developments
A turnkey development provides the tenant with spaces that are fitted out by the developer so that they are ready for use.
These categories do not have standard definitions, and so it is very important that contract documentation sets out precisely what work is to be carried out and by who, rather than relying on ambiguous short-hand terms.
An agreement to lease between landlord and tenant should clearly define:
- What comprises the shell and core built by the developer, including space provision in common areas for tenant equipment such as standby generators, extra chillers, or uninterrupted power supply plant.
- What constitutes category A fit out installed by the tenant but funded by the developer/landlord.
- What tenant equipment is to be installed in common areas.
Category A capital allowances might also be a factor in agreement to lease negotiations.
A rent-free period may be provided by the landlord as a notional contribution to the tenant’s fit out. It not unusual for a tenant to start fitting out their areas before completion of the shell and core works, although the rent-free period will be triggered by practical completion of the shell and core works.
The tenant’s fit out may involve rectifying problems in the developer's works. In order to meet the fit-out timetable these may be funded by the tenant who may then make a claim to recover their costs.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.
The interesting point is who claims the capital allowances tax break which can be substantial as 60% of fit out costs can be the cost of mechanical and electrical services which qualify for depreciation and tax relief. Cat A capital allowances might be a negotiating factor in the agreement to lease negotiations.