First fix
First fix (sometimes described as shell and first fix ) is a short-hand term used to describe the processes that are undertaken during construction works up to the point of applying internal surfaces – typically plaster. It is normally used in relation to the work of specific trades such as carpenters, plumbers and electricians.
Generally first fix will include constructing the structure, cladding, flooring, doorframes, stairs and so on and installing cables for electrical and ICT distribution, pipework for water and gas distribution and heating ventilating and air-conditioning (HVAC) distribution. First fix is not normally visible when looking at the finished building. Where possible first fix should be tested before second fix (for example, plumbing riser stacks).
Second fix takes place after the internal surfaces have been applied. It comprises those items that are visible in a finished area and are held back to avoid damage, or sadly sometimes theft. This may include fitting internal doors, skirting, architraves, handrails, fixtures and fittings, including connection of appliances (such as electrical equipment, sanitaryware, radiators, and so on) testing and commissioning. For more information see: Second fix.
Typically there will be a change of trades operating on the site, and a break in activity for some trades between first and second fix.
In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture-lit artwork and fabrics.
As first fix, second fix and third fix do not have accurate standard definitions, it is very important that contract documentation sets out precisely what work is to be carried out and by who, rather than relying on ambiguous short-hand terms.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines first fix as: ‘Work done in a new building up to the point that plaster is applied to walls, typically including (but not limited to) pipework, cable runs and back boxes. This term is typically used in housebuilding but may also be used in other types of project. While there is no universal definition, it generally relates to work done by plumbers, electricians and other trades on their first visit to a house.’
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
To take part in a discussion, click 'Add a comment' above.
Generally first fix is not visible when looking at the finished article. Where possible first fix should be tested prior to second fix such as plumbing riser stacks. Second fix comprises those items that are visible in a finished area and are held back to avoid damage, perhaps paintwork or sadly sometimes theft. In hotels and residential work there is sometimes a third fix of fixtures and fittings of high value that require fitting or service connections such as chandeliers, white goods, picture lit artwork and fabrics.