Estimate
The term ‘estimate’ is a very broad one that refers to any activity that attempts to quantify something. In the construction industry, it is typically used in relation to the approximate costs associated with a construction project, used, for example to assess the viability or affordability of the project or aspects of it.
An estimate is an attempt to predict the likely expenditures associated with a project as accurately as possible. The degree of detail and the accuracy of estimates will typically increase as the project progresses, more decisions have been made, and more information is available, however, their true accuracy only becomes apparent once the project is complete and the actual costs incurred.
At the outset, estimates may be made to help determine whether a project is affordable and to set a budget. They will then be used to test design options to ensure they are in line with the budget.
A pre-tender estimate (PTE) is a final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers.
Contractors, subcontractors and suppliers will then prepare definitive cost estimates to submit tenders in the construction bidding process to compete for the award of contracts.
There are a number of methods available for estimating, depending on the stage of the project and the information available:
- Benchmarking, which is a process by which other similar projects are used as comparisons.
- Breaking down an overall estimated construction cost into percentages for different elements, based on the experience of the cost consultant.
- Measuring defined quantities from drawings.
For more information see: Types of estimating.
Initial cost estimates might include wider project costs that the client might incur, such as; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on. Later in the project, estimates are likely to focus on the construction cost of the project. It is important to be clear therefore what costs are being included in estimates, and estimates might be accompanied by a schedule of the assumptions that have been made.
Estimates will generally include contingencies, which are downside risk estimates that make allowance for unknown risks associated with a project. At the preliminary business plan stage, estimates might include a 15% contingency, but this may then be reduced as the project progresses and risks pass.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines estimate as: A prediction or forecast of the resources (i.e. time, cost, materials, etc.) required to achieve or obtain an agreed scope of work (i.e. for an investment, activity, project, etc.).’
[edit] Related articles on Designing Buildings
- Analogous estimating.
- Base cost estimate.
- Benchmarking.
- Bottom-up estimation.
- Budget.
- Building works estimate.
- Cash flow projection.
- Common mistakes in bill of quantities.
- Contingencies.
- Cost overruns.
- Cost plans.
- Elemental estimating.
- Elemental method.
- Estimator.
- Expert opinion estimating.
- Extra over (EO).
- Initial cost appraisal.
- Irrelevant cost.
- Operational rate estimate?.
- Order of cost estimating.
- Parametric estimating.
- Post tender estimate.
- Pre-tender estimate.
- Spon's Price Book.
- Tender pricing document.
- Three point estimation.
- Top down estimating.
- Types of estimating.
- Unit rate estimating.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.