Commencement of construction works
In very broad terms, the word ‘commencement’ means beginning something. In the construction industry this generally refers to the contractor beginning the construction works, ie the point at which site clearance, demolition, excavation or construction begins. For more information see: Construction operations definition.
Commencement of construction works will be proceeded by activities such as design, procurement and mobilisation, and there may be legal requirements that need to be satisfied, such as obtaining planning permission, satisfying planning conditions or planning obligations, obtaining building regulations approval, obtaining a party wall agreement, notifying the Health and Safety Executive and so on. For more information see: What approvals are needed before construction begins.
In addition, commencement may be required before a certain point, for example, within 3 years of the date planning permission was granted, or within three years from the date of deposit of plans for building regulations approval.
Commencement may also have contractual implications, as the date for possession of the site by the contractor may be set out in the contract. If the client fails to give possession of the site to the contractor, and there are no provisions for delay in the contract, then they will be in breach of contract. Even if the contract does provide for delay in giving possession of the site to the contractor, the contractor may still be able to claim for an extension of time and perhaps loss and expense.
If no date for possession is included in the contract, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
On commencement of the works, the contractor may become responsible for insurance, security of the site and so on, and may be obliged to progress regularly and diligently with the works, or to achieve certain key dates.
The term ‘commencement’ might also be used to refer to the commencement of an appointment, the commencement of a contract, commencement of legal proceedings and so on.
NB There is currently no legal UK definition of (as opposed to guidance on) "commencement" for the purposes of the building regulations. Knowing whether work has commenced will be critical to understanding whether approval has lapsed and/or whether work benefits from transitional provisions. Consequently, a legal definition of "commencement" is being considered.
[edit] Related articles on Designing Buildings
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.