CIBSE Case Study: Christchurch International Airport
Article from the May 2015 edition of the CIBSE Journal written by Andy Pearson.
Christchurch International Airport’s new terminal features a water source heat pump system with a payback period of only two years. Andy Pearson looks at an innovative system that triumphed in the International Project of the Year category at the CIBSE Building Performance Awards 2015.
The new three-storey terminal at New Zealand’s Christchurch International Airport was the first major infrastructure project to be completed on the South Island after the devastating earthquakes of 2010 and 2011. It is fitting then that the 30,000m2 building relies on artesian water, abstracted from beneath the Earth’s surface, to provide an innovative, energy efficient, cost-effective and environmentally benign heating and cooling solution.
The artesian system was designed by the New Zealand office of multinational consultancy Beca. Since the completion and opening of the NZ$237m (£121m) terminal in 2013, it has dramatically reduced the operational costs of the building and its dependency on fossil fuels. The airport operating company has been so impressed with the cost savings that it is implementing a similar artesian water-based set-up at the airport’s existing international terminal.
The system’s success is not confined to the airport; artesian arrangements for sustainable heating and cooling are under design or in construction at a number of other developments in the city. This potential legacy was recognised by the judges of the CIBSE Building Performance Awards 2015, who gave top honours to the scheme in the International Project category. They described the artesian solution as: ‘An innovative application, with very good collaboration and strong ongoing involvement, and lots of potential for wider involvement.’
Work started on the scheme in 2005. Along with architect Warren and Mahoney, in association with Hassell (Australia), the firm designed a new terminal – incorporating an integrated domestic and international check-in – to sit on the site of the original 1960s domestic terminal. It was to be constructed in phases as the original terminal was progressively demolished, to make sure the airport could continue to operate. As a consequence of this phased construction, the services had to be designed to ensure the new terminal’s plantrooms and services were up and running before the existing ones were dismantled. ‘The first stage of the new construction had to contain the central plant to enable the new terminal to operate as a stand-alone building,’ explains Justin Hill, Beca’s technical director, building services. As subsequent construction phases were completed, the new systems were extended to service these too.
‘The new terminal had to be designed so that its building services could be extended as new areas were built; this included, for example, the use of differential pressure control valves on the heating and chilled water systems, so the operational areas did not need to be recommissioned as new areas were constructed,’ Hill adds.
The client’s brief for the integrated terminal was for it to be as energy efficient and sustainable as possible within the constraints of the budget. ‘The use of artesian water was always on the cards as the existing international terminal uses it directly in a pre-cooling application, ’ Hill says. ‘The challenge for Beca was to make better use of artesian water and to eliminate the need for fossil fuels. ’
The elegance of the system is that it uses standard equipment – including three chillers – which have been configured to enable them to provide simultaneous heating and cooling, with the ability to recover and redistribute energy around the building. ‘The idea arose when Keith Paterson (business director for Canterbury Rebuild) realised the temperature of the artesian water – at 10-12°C – was perfect for a heat pump type application and configured the system in a similar manner to that used in the thermal storage industry, which Keith had experience of from his work in Singapore, ’ Hill recollects. The system comprises two principal circuits: a closed-loop secondary system and an open artesian water circuit. In the open circuit, artesian water is abstracted from five wells, which draw water from a major aquifer flowing 35m beneath the terminal. There is provision to add a sixth well, should the capacity of the system need to be increased in the future.
These boreholes are located 50-75m apart, and relatively close to the terminal, to keep pipe runs to a minimum. Abstracted artesian water passes through any one – or all three – of the heat exchangers before being discharged back into the ground via a 5m-deep soak pit beneath the car park. No water is consumed by the system; the only effect is that the temperature of the returned water will vary from 7-20°C, depending on the plant’s mode of operation.
With the closed-loop system, water circulates through the secondary side of the heat exchangers, the air handling unit heating and cooling coils and, if required, the chillers when they operate as water-to-water heat pumps. When cooling loads are low, water from the aquifer can meet the terminal’s cooling requirements. This avoids the need for any mechanical refrigeration. Areas requiring year-round cooling have coils sized to enable them to use artesian temperature cooling year-round, to minimise the use of the chillers.
With higher heating or cooling loads, the artesian water is used as part of a mechanical refrigeration system, with the chillers working as geothermal heat pumps, thereby enabling the system to provide heating and cooling simultaneously, and in any proportion, from every chiller. In this mode, the heat energy removed by the chiller in the evaporator to generate chilled water is used to provide heat. Rather than reject the heat energy – generated as a by-product of providing cooling through cooling towers to the atmosphere, the chiller’s condenser water is used as a heat source for the terminal’s heating circuit. This enables the system simultaneously to generate heating and cooling. When heat is not needed by the terminal, it is rejected to the artesian water via the plate heat exchangers.
‘When we want to generate heat, if there is no requirement to chill the terminal’s cooling water system we, effectively, chill the artesian water, ’ explains Hill. ‘To my knowledge, there are no artesian-based systems elsewhere, of this size and nature, configured to provide simultaneous heating, cooling and artesian temperature cooling with the ability to recover and redistribute energy around the building.’
Comprehensive engineering analysis was undertaken to assess the most appropriate solutions and to provide confidence that the system would achieve the design objectives. This resulted in the central plant having four modes of operation: artesian cooling; mechanical cooling; heating; and simultaneous heating and cooling. Water temperatures in heating mode were analysed to optimise the flow and return temperatures. Operational efficiencies and capital cost – along with reliability and plant longevity – were all considered at various LTHW temperatures. The analysis showed the optimal temperature for heating to be 40°C flow and 25°C return.
In addition to heat from the chillers, heat is recovered from two 1MW electrical generators, when they operate, and is added to the LTHW system. The generators were installed to ensure the terminal can continue to operate in a power cut and – at the request of the terminal’s electricity supply company – to operate during periods of peak electrical demand. The chillers are more than capable of supplying sufficient heat for the building, but the heat is recovered because it is cost effective to do so.
The heating and chilled water systems have been designed with floating water temperature set-points to maximise efficiencies of the central plant. The heating water circuit flow temperature has been designed to float between 30°C and 40°C, depending on the heating requirement of the building. If, for example, there is a reduction in the building’s heating demand, the heating water flow temperature set-point is reduced gradually until the temperature of the heating water meets the demands of the building. This improves the efficiency of the chiller as a heat source for the building.
The company spent a long time developing and bench-testing a robust control strategy for the artesian system. ‘We did not set out to provide the optimum and most efficient control strategy, but rather one that was reasonably efficient, and – most importantly – stable and robust, and capable of handling all possible scenarios,’ says Hill. ‘Using this as a base, the control strategy can be optimised and the system efficiency improved, based on actual building performance and usage.’
In July 2013, four months after completion of the terminal, the new and existing international buildings’ energy consumption – which includes all energy sources, equipment and tenancy loads – was measured at 27.97kWh/(m2·month). As part of a soft landings approach (apt for an airport) over the following year, the engineers – after fine-tuning – reduced this figure to 27.01kWh/(m2·month), which equates to an annual figure of 324kWh/m2.
Once the system was complete and its performance established, Beca undertook a study of the performance of the central plant system. During the period analysed, the total annual heating consumption was 2,860MWh for the new terminal, while annual cooling was 3,170MWh. The electrical input to the chillers was 901MWh, which equates to 34.7kWh/m2 for the 26,000m2 of conditioned floor area, giving an overall coefficient of performance (CoP) of 6.7 for the central chiller system, excluding pumping energy. This corresponds to CO2 emissions of 5.9kgCO2/m2, based on the New Zealand Green Building Council Green Star calculator.
The study showed that, with some modifications to the chiller control strategy, annual central plant energy could be reduced by 100MWh – approximately 10% of the chiller input power – which, excluding pumping energy, would increase the overall central chiller system CoP to 7.5. The cost of the artesian-based system over and above a conventional boiler, chiller, cooling tower system was approximately NZ$750,000 (£375,000). Based on in-use data of 6,030MWh of thermal and 901MWh of electrical input energy, payback on the solution is approximately two years.
Hill says that the payback period alone has ‘justified retaining the system, rather than opting for a cheaper conventional solution during the project’s various rounds of value engineering’. The final word on the scheme should be left to Mike Parker, the terminal’s facilities manager: ‘We are ecstatic with the artesian heating and cooling system. ‘During the many rounds of value management, the system came under heavy scrutiny and pressure to be dropped for a more conventional and cheaper solution. Thankfully, Beca and Christchurch Airport were well aligned and retained the system, which is performing better than we could have hoped.’
Four Modes of Operation:
- Mode 1: Artesian cooling. Artesian water at 10-12°C is used to cool the secondary circuit directly to reduce, or even avoid, the need to run the chillers.
- Mode 2: Mechanical cooling. The chillers provide chilled water, with the artesian water used to remove heat from the condensers.
- Mode 3: Heating. Artesian-temperature water is used as the heat energy source for the chiller evaporators to generate hot condenser water for use in the heating circuits.
- Mode 4: Simultaneous heating and cooling. Recovering and redistributing energy around the building, using condenser-heated water in the secondary heating circuit and evaporator chilled water in the secondary cooling circuit, with artesian water used as the heat source or heat sink, depending on the imbalance between cooling and heating loads.
For the full article on the --CIBSE website click here.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.