Bonds in construction contracts
Contents |
[edit] Introduction
Bonds are a means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor. The cost of the bond is usually borne by the contractor, although this is likely to be reflected in the contractor's tender price.
Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
See also Bonds v guarantees.
[edit] Performance bond
A performance bond is commonly used as a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client, although they can also be required from other parties.
Performance bonds are typically set at 10% of the contract value. This compensation can enable the client to overcome difficulties that have been caused by non-performance of the contractor, such as, finding a new contractor to complete the works.
For more information, see Performance bond.
[edit] Advance payment bond
If the client agrees to make an advance payment to the contractor, (for example where the contractor incurs significant start-up and procurement costs before construction begins), a bond may be required to secure the payment against default by the contractor. This will normally be an on-demand bond.
For more information, see Advance payment bond.
[edit] Off-site materials bond
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’. For example, where a contractor has made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme.
This is similar to the situation where an advanced payment is made in that a bond secures the payment against default by the contractor and is likely to be an on-demand bond. The bond might be up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
[edit] Bid bond (or tender bond)
Bid bonds are rare in the UK, but can be a requirement of an international tender process. They are usually on-demand bonds submitted with a tender to secure the tenderer's commitment to commence the contract. The bond is partially or fully forfeited if the winning tenderer fails to execute the contract or meet other specified conditions.
Bid bonds can be open to abuse by the client and may prevent smaller companies from tendering.
For more information, see Bid bond.
[edit] Retention bond
Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate that is retained by the client. The purpose of retention is to ensure the contractor properly completes the activities required of them under the contract. Half of the amount retained is released on certification of practical completion and the remainder is released upon certification of making good defects.
An alternative to retention is a retention bond, where the client agrees to pay the amounts which would otherwise have been held as retention, but instead a bond is provided to secure the amount that would have been retained. As with retention, the value of the bond will usually reduce after practical completion has been certified.
[edit] Defects liability bond (or defects liability demand guarantee)
The defects liability period (now called the 'rectification period' in Joint Contracts Tribunal (JCT) contracts) begins upon certification of practical completion and typically lasts six to twelve months. During this time, it is the contractor's responsibility to rectify any defects that become apparent in the works.
A defects liability bond can be used to ensure that the contractor continues to provide services, rectifying defects that become apparent after practical completion has been certified. This is generally an on-demand bond that may be required on projects where there are no remaining payments to be made, or other security such as retention, after practical completion.
[edit] Adjudication bond
Adjudication is a contractual or statutory procedure for swift dispute resolution. Adjudication is provided by a third-party adjudicator selected by the parties to the dispute.
Adjudication bonds are conditional bonds that have emerged on PFI/PPP projects and are payable on an adjudicator's decision. Adjudication bonds are most suitable when the adjudicator’s decision is final and binding. If this is not the case (i.e. the adjudicator’s decision is an interim one), complex procedures are necessary to balance payments if subsequent dispute resolution procedures reach different decisions.
[edit] Related articles on Designing Buildings
- Advance payment bond.
- Bid bond.
- Bonds and guarantees.
- Bondsman.
- Campaign for cash retentions reform.
- Comfort letter.
- Contractor bonding.
- Escrow.
- Parent company guarantee.
- Performance bond.
- Professional consultant's certificate.
- Retention.
- Retention bond.
- Surety.
- Warranty.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA (2013).
- Zero-coupon bond.
Featured articles and news
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Comments
If you need Performance Bonds, Nationwide Sureties have a number of options that can assist you at tender or after winning your Contract, to help you deliver.