Third party dependencies for building design and construction
Not every aspect of a project is within the direct control of the client or their project team. Every project is dependent to some extent on third parties. It is important that these third party dependencies are identified and that their potential impacts are understood, quantified and managed.
Third parties may not be motivated by the same objectives as the client or project team, but nevertheless they can have a serious impact on the programme for a project. It is not safe to assume, just because a time allocation has been made within a programme for a third party dependency, that the third party has any interest in keeping to that programme.
These third parties are often different from stakeholders in that they may have no interest in the project or any ability to affect decisions, and yet they may still be in a position to impact upon success.
Third parties can even be responsible for completely unrelated, circumstantial dependencies, such as the legislative framework. For example, the introduction of changes to the building regulations can have a very significant impact on a project and yet are entirely beyond the control of the project team.
The range of potential third party dependencies is very wide and will vary from project to project, but may include:
- Neighbours (planning matters, party wall matters, access and other permissions, easements, right to light, tree rights and so on).
- Licensing authorities.
- Planning authorities.
- Building control.
- Other statutory authorities and non-statutory authorities (Health and Safety Executive, Environment Agency, Civil Aviation Authority, English Nature, Historic England, CABE, Highways England and so on – see Statutory authorities for more information).
- Utilities companies and other statutory undertakers.
- Purchasers or vendors of land or properties.
- Archaeological or other surveyors (surveys can reveal issues such as; archaeological remains, unexploded bombs, asbestos, contamination, japanese knotweed, roosting bats, great crested newts, tree preservation orders and so on that can cause very significant delays to a project).
- Dependent projects (for example decontamination of the site by a third party prior to sale of land to the client).
- Funding availability.
- Local Chambers of Commerce.
- Politicians.
- Competitors.
- The supply market (goods, labour, plant, equipment and so on).
- Unions.
- The availability of third party services (such as local schools, feeder organisatons, local transport, local infrastructure and so on.)
- The political and legislative framework.
- The wider economic context.
- Customers.
- Emergency services.
- Community groups.
- Special interest groups.
- The press.
Identifying and assessing these third party dependencies should involve the whole project team, and can be best carried out at a project workshop (for example it may form part of a risk workshop – see risk register for more information). Techniques such as PEST analysis (Political, Economic, Social, Technological) can help identify third party dependencies.
It is important that this is not simply a paper exercise. The probability and importance of impacts should be assessed so that resources can be prioritised, responsibilities allocated and strategies put in place to monitor progress (see stakeholder and stakeholder map for more information about how this might be done).
Where risks remain, strategies should be put in place to mitigate, transfer, avoid or accept those risks. See risk register for more information.
[edit] Related articles on Designing Buildings Wiki
- BREEAM independent party.
- Collaborative practices.
- Consultation process.
- Dependency.
- Early BREEAM stakeholder engagement.
- Externalities.
- Independent third party.
- Interested party.
- Receptor.
- Risk management.
- Risk register.
- Stakeholders.
- Stakeholder management: a quality perspective.
- Stakeholder map.
- Statutory authorities.
- Statutory undertakers.
- Technical due diligence.
- Utilities.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.