Rights to light
Contents |
[edit] Introduction
The right to light in the UK goes back to general property law relating to easements that from the rule of William IV. The Ancient Lights Law was superseded by the 1832 Prescription Act.
Rights to light generally become an issue when a new development, or proposed development affects the access to light of an adjoining property. Rights to light also apply to obstructions caused by trees, hedges and so on, but there are no rights to light for open ground.
Rights to light can be the result of 'easements', or can be ‘nuisance’ issues.
- An easement is a a right which a person has over land owned by someone else. An easement can be created by express grant (for example it may be set out in a conveyance deed), by necessity (for example if there is only one means of access to a site) or by prescription (the act has been repeated for at least 20 years). Easements are normally attached to the land. In relation to rights to light, an easement can perpetuate even if a new building is constructed. This means that it cannot be assumed that no rights to light exist simply because neighbouring buildings appear to be new.
- Private nuisance regulates interference with a persons right to enjoy land, or some right in connection with that land. Such interference must be ‘unreasonable’ to constitute nuisance. Nuisance can be remedied by an injunction, abatement and/or damages.
[edit] Interpretation
Generally, a right to light refers to the right to receive sufficient light through an opening (such as a window), allowing ‘ordinary’ comfortable use and enjoyment of a dwelling, or ‘ordinary’ beneficial use and occupation of other buildings.
The levels of acceptable light have not been objectively quantified and are instead assessed on a case-by-case basis by the courts. The terms 'sufficient light according to the ordinary notions of mankind' and 'tangible deprivation to a building' have earned substantial fees for the legal and surveying professions and given rise to specialists and expert witnesses in this field.
Much depends on:
- The measurement of light.
- Proof of its diminution.
- The damage caused by obstruction.
[edit] Obstruction
Windows can be of different sizes, heights and quantity and serve varying room sizes with natural light. Generally, the larger the area served by a window, the more value can be put on to the window.
The obstruction of light between an internal space of the dominant property and the sky by a servient property is generally caused either by the height, width or proximity of the offending structure. The general law on easement does not allow a servient property to benefit in value at the expense of the dominant property if the latter has enjoyed uninterrupted rights for twenty years or more.
[edit] Measurement
It is now relatively straightforward to measure, or model lighting levels on working planes within buildings and to assess whether there is currently adequate light to perform tasks such as reading, or whether there will be once a proposed development is constructed.
[edit] Rules of thumb
The '45 degree rule', which may be used to assess planning applications for developments impacting on windows, is not used to assess rights to light.
The '50:50 rule' however, may be deemed adequate. This involves determining what percentage of a room receives adequate light on a working plane 850 mm above the floor. An injury may be considered to have occurred where the percentage is reduced to less than 50%. Where more than 50% of the room still receives adequate light however, an injury may not be considered to have occurred, irrespective of the amount of light that has been lost.
[edit] Remedies
The most likely remedy to a loss of a right to light is an injunction. Courts do not like to award damages in such cases, as this could be seen as a developer being able to ‘buy’ the rights of another. However, if damages are awarded, they may be based on:
- The historical use and purpose of the rooms affected by the infringement.
- The loss of natural light power over the affected by the obstruction.
- The additional value to the property of the servient offender. This may be a proportion of the developers profits, where the proportion relates to the amount of floor space that the developer could not have built if they had not infringed on the right to light of their neighbour.
- Any loss of residual value to the dominant property
The law and possible remedies surrounding rights to light are not straightforward. There are complications in relation to some Crown land, statutory bodies and compulsory purchase, and under certain circumstances developers can obtain light obstruction notices. For more information, see Light obstruction notices.
If it is possible that a development will encounter rights to light issues, a right to light consultant can be appointed to give expert advice.
In practice, the dominant property can hold up a development for a very long time by means of an interlocutory injunction. The delay caused while the case goes through the courts, particularly if it is appealed, can bring everything to a halt. So a negotiation generally takes place, with the dominant owner’s team having a good idea of the value of the infringement to the servient owner, and a deal is done or the design is changed to step back any light obstructing structures.
[edit] Recent considerations
Until recently, it was considered that a right to light by prescription may be lost if a person submits to a loss of light for a year before making a claim. This means that complaints should be made quickly, and repeated frequently to ensure that the right is not lost before the claim is made. However, the case of HKRUK II (CHC) Ltd v Heaney (2010) suggests that time may no longer be a barrier to an injunction.
See also Light obstruction notices.
In 2013, the Law Commission launched a consultation paper proposing radical reform to rights to light to prevent them from becoming an unnecessary constraint on development. The consultation ran from 18 February 2013 to 16 May 2013 (See The Law Commission: Consultation Paper No 210, Rights to Light, A Consultation Paper). The key recommendations, were published on 4 December 2014, in Final Report, Rights to Light (Law Com No 356) and included:
- A statutory notice procedure which would allow a landowner to require their neighbours to tell them within a specified time if they intend to seek an injunction to protect their right to light, or to lose the potential for that remedy to be granted.
- A statutory test to clarify when courts may order damages to be paid rather than halting development or ordering demolition.
- An updated version of the procedure that allows landowners to prevent their neighbours from acquiring rights to light by prescription.
- Amendment of the law governing when an unused right to light is treated as abandoned.
- A power for the Lands Chamber of the Upper Tribunal to discharge or modify obsolete or unused rights to light.
A High Court ruling in 2023 in a dispute between William Ellis McLennan and Medway Council, found that the impact of a development on a neighbour’s solar panels was capable of being a material consideration in planning. Ref https://www.building.co.uk/legal/why-it-is-important-to-consider-solar-panels-in-planning-applications/5121313.article
[edit] Related articles on Designing Buildings
- Adequate view out.
- BREEAM Visual comfort View out.
- Easements.
- Light obstruction notice.
- Light pollution.
- Lighting of construction sites.
- Openable window area.
- Party Wall act.
- Quiet enjoyment.
- Restrictive covenants.
- Right of support.
- Right to a view.
- Rights over land.
- Rights to light in the US.
- Rights of way.
- Site layout planning for daylight.
- Tree preservation order.
- Tree rights.
- View.
- Working plane.
[edit] External references
- Rights of Light Act.
- The Prescription Act.
- RICS: Rights of light: Practical guidance for chartered surveyors in England and Wales.
- The Law Commission: Consultation Paper No 210, RIGHTS TO LIGHT A Consultation Paper.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.