Advance payment bond for construction contracts
If the client agrees to make an advance payment (sometimes referred to as a down payment) to a supplier, a bond may be required to secure the payment against default by the contractor. This is referred to as an advance payment bond (APB), advance payment guarantee or advance stage payment.
For more information, see Advance payment.
Typically on a construction project an advanced payment bond will be required by the client if the contractor requests advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins.
For example, where the contractor has had to purchase high-value plant, equipment or materials specifically for the project. The bond will protect the client in the event that the contractor fails to fulfil its contractual obligations, for example if the contractor becomes insolvent.
An advance payment bond will normally be an on-demand bond, meaning that the bondsman pays the amount of money set out in the bond immediately on demand, without any preconditions having to be met. This is as opposed to a a conditional bond (or default bond) where the bondsman is only liable if it has been established that there has been a breach of contract.
Advance payment bonds must be very carefully drafted to set out the circumstances for payment and to make clear that they are on-demand bonds.
A ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Vesting certificate.
[edit] Related articles on Designing Buildings
- Advance payment.
- Bid bond.
- Bonds in construction contracts
- Bonds and guarantees.
- Escrow.
- Materials on site.
- Off-site goods and materials.
- Off-site goods and materials - legal issues.
- On-demand bond.
- Parent company guarantee.
- Performance bond.
- Retention.
- Retention bond.
- Vesting certificate.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA.
- Zero-coupon bond.
[edit] External references
- Rainy Sky S.A. v Kookmin Bank.
Featured articles and news
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Key points and relevance to construction of meeting, due to reconvene.
Comments