Thames tideway tunnel
Contents |
[edit] Introduction
The £4.2bn (at 2011 prices) Thames tideway tunnel project comprises a 24km long 7.2m diameter sewer 60m (average) below ground. The project plans were approved by the government on 12 September 2014. The tunnel will run from Acton in the west to Abbey Mills in the east. It will have a holding storage capacity of 1.6 million cubic metres.
Its purpose is to protect the River Thames from the frequent overflow of Victorian sewers designed for a much smaller population. Recently, flash flooding has caused sewers to back up and flood residences in west London.
Its route generally follows the Thames, at a fall of 1 in 790, it intercepts 34 overflow facilities and will require a number of significant connecting tunnels to other existing sewers. The project also includes new, expanded or replacement pumping stations, increased capacity storm water holding tanks and expanded sewage treatment works at Beckton which will capture the new tunnel contents via the newly constructed Lee Tunnel.
[edit] Procurement
Thames Water (via a special purpose vehicle, Thames Tideway Tunnel Ltd) tendered the main tunnel work to the international market in three sections. UK consortia have been selected for all three projects:
- West section £300m - £500m, Nuttall and Morgan Sindall.
- Central section £600m - £900m, Laing O'Rourke and Ferrovial Agroman.
- East section £500m - £800m, Costain and Vinci and Bachy.
[edit] Construction
Construction is due to start in 2016 and complete by 2023. There are 23 construction sites. Some are on land already owned by Thames Water and others are on new sites still to be acquired, particularly those on the Thames foreshore.
The river will be used as much as possible to remove excavated material and deliver tunnel segments and construction material. At the combined sewer overflow (CSO) interception sites, construction of vertical cylindrical shafts some 60m deep will be built with internal diameters ranging from 7m to 20m to enable connecting culverts to be constructed that link existing sewers to the new tunnel. The main drive sites will require even larger 30m diameter x 60m deep shafts to allow the tunnel boring machinery to be lowered into position.
[edit] Sites (west to east)
- Acton Storm Tanks - main tunnel starting point and combined sewer overflow (CSO) interception.
- Hammersmith - pumping station, CSO interception and connection tunnel drive site (CTDS).
- Barn Elms – CSO interception and CTDS
- Putney Embankment Foreshore – CSO interception and CTDS
- Carnwath Road Riverside – Main tunnel drive reception and connection tunnel from Dormay Street reception site.
- Dormay Street – CSO interception and CTDS.
- King George's Park – CSO interception and connecting tunnel reception site.
- Falconbrook – pumping station CSO interception and CTDS
- Cremorne Wharf Depot – CSO interception and CTDS
- Chelsea Embankment Foreshore – CSO interception and CTDS
- Kirtling St – main tunnel double drive site
- Heathwell Pumping Station – CSO interception and CTDS
- Albert Embankment foreshore – CSO interception andCTDS
- Victoria Embankment foreshore – CSO interception and CTDS
- Blackfriars Bridge Foreshore – CSO interception
- Shad Thames Pumping Station – system modification
- Chambers Wharf – main tunnel drive and reception site
- Earl Pumping Station – CSO interception
- Deptford Church St – CSO interception
- Greenwich Pumping Station – CSO interception and CTDS
- King Edward Memorial Park – CSO interception
- Bekesbourne St – system modification
- Abbey Mills Pumping Station – Main tunnel reception site.
[edit] Funding
Thames Water are to fund £1.4 billion by spreading the cost across its consumers. This could add £80 to average annual bills by 2020 across its 15m customers. Thames Tideway Tunnel Ltd will raise £2.8 Billion (2011 pricing) for the capital works based on future revenue income contracted with Thames Water.
In July 2015, it was announced that Bazalgette Tunnel Limited would finance, deliver and own the sewer. This is a consortium consisting of Allianz, Amber Infrastructure Group, Dalmore Capital Limited and DIF.
[edit] Progress
In 2017 it was reported that ahead of tunnelling in 2018, the main focus of work had been at the three main drive sites. These are for launching the 7.8 m diameter tunnel boring machines (TBMs) and will serve as material transport hubs and head offices for each of Tideway's three main NEC3 works contracts – west, central and east. For more information see: Thames Tideway update.
In February 2020 it was reported that tunnellers had passed the halfway mark on the £3.8bn project.
In September 2020 it was reported that the main tunnel drive for the first major section of the tunnel had been completed.
[edit] Related articles on Designing Buildings
- Are sustainable urban drainage systems the response to our changing climate?
- Civil Engineering during the Industrial Revolution in Britain.
- Masterplanning.
- Public sewer.
- Pumping station.
- Safety lessons the space industry can teach engineers.
- Sewer construction.
- Sewerage.
- The redevelopment of Leicester's sewerage system by Joseph Gordon.
- Thames Gateway.
- Thames Tideway update.
- Tunnel.
- Understanding and managing workplace stress is critically important to civil engineers.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February