Self-build home: Prepare a concept design
Introduction.
In this stage, we attribute design activities to ‘designers’. These may be architects and engineers, a design and build contractor, or a kit house supplier. If a kit house supplier is only supplying the house itself, additional design consultants may be required.
Concept design is the first design stage. Some designers will differentiate between 'concept design' and 'scheme design'. In this case, the 'concept' is the initial design idea (or outline design), whereas the 'scheme' develops the concept, taking on board more functional and practical considerations.
It may be necessary for designers to undertake site surveys and other site appraisals before starting the concept design, for example, digging trial pits before designing foundations.
Design is an iterative and collaborative process, it requires close involvement of all those with an interest in the completed home. This is important not only to ensure a suitable design is developed, but also to make certain that everyone has ‘bought into’ the design and it is not just one person’s vision.
Developing the brief.
It is likely that the project brief will continue to develop as the concept design is prepared. It is important that these developing requirements are written down so there is a record of what has been agreed. Development of the brief might include:
- Preferred style and materials.
- Requirement for spaces to be open plan or enclosed.
- Ability to operate parts of the building separately (for example an office, children’s areas or guest rooms).
- Sound insulation and sound absorption requirements.
- Provision of en-suite or shared bathrooms, dressing rooms and so on.
- Accessibility requirements for people with disabilities or impaired mobility.
- Access to and views of gardens and the surrounding landscape.
- Entry spaces and reception spaces.
- Fireplaces, wood burning stoves and so on.
- Hard v soft floor coverings.
- Security, intruder alarms, cctv, door and gate entry systems and post facilities.
- Audio visual, ICT, entertainment and other equipment requirements.
- Specialist requirements for finishes, fixtures and fittings.
- Orientation in relation to the sun, prevailing winds and views.
- Natural lighting.
- Artificial lighting (general and feature) and controls.
- Comfort conditions (radiant temperature, air temperature, natural and mechanical ventilation and so on).
- Storage requirements and utility rooms.
- Internal and external waste storage and collection.
- The possibility of including enabling works for future extensions.
- Galleries and balconies.
- External landscaping such as; planting, seating areas, drainage, sprinklers and taps, lighting and power, paths, screens, fences, walls, shading and so on.
Developing the concept design.
The concept design should develop to include:
- A site plan, including; access, car parking, hard surfaces, landscape, water features, art and so on.
- Floor plans, sections and elevations.
- Analysis of the relationships between related functions.
- Building services strategy (heating, ventilation, electrical supply, lighting and so on).
- Outline specification describing the main materials and workmanship required.
- Schedules of accommodation.
- A strategy for obtaining planning permission.
- Procurement strategy.
- Programme, construction methodology and logistics.
- Approximate quantities of the main materials proposed.
- A cost plan (including site preliminaries).
This information should be co-ordinated and issued at the end of the stage for comment or approval before the project proceeds to detailed design or a planning application is submitted.
The brief should be frozen at the end of the concept design stage and any subsequent changes that materially alter the cost should be carefully considered by the self builder for approval or rejection.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.