Non-negligent liability insurance
Construction is an inherently dangerous process with many hazards, in particular when working close to existing buildings or other structures. In such situations, there is the potential for that property to suffer damage, even if care is exercised.
As a result of the potential for these sorts of losses to occur on construction projects, Joint Contracts Tribunal (JCT) contract forms provide for non-negligent liability insurance to be taken out, and other forms of contract may have similar provisions, either as part of the standard form or as an amendment.
Such provisions require that the contractor takes out a policy that protects the developer in respect of any expense, liability, loss, claim or proceedings incurred as a result of damage to property from the works being undertaken due to; collapse, subsidence, heave, vibration, weakening or removal of support and lowering of ground water. It is also possible to include cover from the hazards of flood, explosion, backing up of drains and bodily injury to third parties caused by an insured peril.
The cover may be in respect of existing buildings being worked upon and/or property on adjoining land. The policy is issued in the joint names of the employer and contractor.
This sort of cover is not always be required as the kind of activities which give rise to such losses may not be present on all projects. Consultants will usually be able to recommend whether or not the cover is required.
There are a variety of activities that could give rise to the potential hazards covered by the insurance, including:
- Piling and foundation excavations
- Underpining.
- De-watering of the ground
- Demolition close to an existing property.
- Shoring of walls
- Works that may affect the load-bearing capacity of a structure.
- Works on listed buildings or buildings in a poor condition.
Typical exclusions from non-negligent cover might include:
- Damage caused by negligence, omission or by default of the contractor or subcontractor.
- Damage which is due to error or omissions during the design process.
- Damage which could reasonably have been foreseen as inevitable.
- Penalties incurred under contract and damages for breach of contract.
The Royal Institute for Chartered Surveyors (RICS) have produced a guidance note which provides further information on non-negligent liability insurance, including details of Gold v Patman & Fotheringham (1958), the landmark case in this situation.
[edit] Related articles on Designing Buildings Wiki.
- 3D animation for insurance risk analysis.
- Building Users' Insurance Against Latent Defects.
- Contractors' all-risk insurance.
- Contract works insurance.
- Directors and officers insurance.
- Employer's liability insurance.
- Flood insurance.
- Insurance.
- Insurance terminology.
- Integrated project insurance.
- Latent defects insurance.
- Legal indemnity insurance.
- Professional Indemnity Insurance.
- Public liability insurance.
- Residual value insurance.
[edit] External references
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February