Measured quantity
Quantity is a measurement of a physical entity in units that depend on the nature of that entity. Therefore, quantity indicates how much of something exists, existed or will exist.
In construction, ‘measured quantities’ typically form part of a bill of quantities (BoQ) and indicate how much of something will be required to construct a building or part of a building.
Usually prepared by a quantity surveyor (QS), the BoQ provides project-specific, measured quantities of the items of work identified by the drawings and specifications (which form part of the tender documentation). For example, in a traditional building, the BoQ will contain measured quantities for each item that goes to make up the final construction e.g bricks, doors, ironmongery, floor tiles, roof slates, etc. This means that potential tenderers know exactly how much of a given quantity will be required for the work and so they can price for it. This creates a level playing field as all tenderers are pricing for the same measured quantities which allows the client to make easy comparisons between the bids.
Measured quantities are typically expressed in number (e.g door handles), length (e.g handrails, kerbs), area (e.g floor tiles, plaster), volume (e.g concrete) or weight (e.g gravel).
When prices have been entered by a tenderer beside each measured quantity in a BoQ, this constitutes the tenderer’s offer.
Not providing measured quantities would require that the various tenderers on a project ‘take off’ the quantities themselves. With numerous tenderers with possibly different methodologies, as well as human error creeping in, the quantities taken off would vary, thus making the client’s job in comparing the tenders that much harder.
The New Rules of Measurement (NRM) are published by the Royal Institution of Chartered Surveyors' (RICS) Quantity Surveying and Construction Professional Group. They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects. Adopting a standard methodology such as NRM facilitates consistency and benchmarking and helps avoid disputes.
NRM is a suite of documents, comprising three volumes; NRM1, NRM2 and NRM3.
Fore more information see: New rules of measurement.
In some circumstances, it may be difficult to determine exact quantities, for example early in the development of a project. In this case approximate quantities may be estimated. These should be accompanied by a schedule of the assumptions made in determining the approximate quantities.
For more information see: Approximate quantities.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill.
- Taking off construction works
- Bill of quantities breakdown structures BQBS
- Types of bill of quantities
- Standard Method of Measurement SMM7
- Preliminaries in construction
- Schedule of rates for construction
- Bill of quantities software
- Tender documentation for construction projects
- Approximate bill of quantities
- How to take off construction works
- Specification for construction
- Advantages of a bill of quantities
- New Rules of Measurement
- Typical tender process for construction projects
- Priced bill of quantities
- All-in rates
- Common mistakes in bill of quantities
- Bill of quantities v Schedule of rates
Featured articles and news
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.