Bill of quantities v Schedule of rates
Contents |
[edit] Introduction
This article explains the difference between a bill of quantities (BoQ) or a schedule of rates on construction projects. Both can be used to obtain prices from contractors and for valuing variations. The decision about whether to use a bill of quantities or a schedule of rates depends on the nature of the project as well as the chosen procurement route.
[edit] What is a bill of quantities?
A bill of quantities is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of quantities constitutes the tenderer's offer.
Typically a bill of quantities will be appropriate on projects that have been designed in detail, and so the precise quantities required are known.
For more information see: Bill of quantities.
[edit] What is a schedule of rates?
A schedule of rates is a list in a contract setting out the staff, labour and plant hire rates that the contractor will use for pricing cost reimbursable instructed daywork. It does not contain any quantities for the specific work items and is typically used when the nature of work required is known but it cannot be quantified, or if continuity of programme cannot be determined.
On a much larger scale, a similar process might be used on a 'schedule of rates term contract', 'term contract' or 'measured term contract'. Tenderers quote unit rates against a document that is intended to cover all likely activities that might form part of the works. As the extent of the work is unknown, the unit rates include overheads and profit. General preliminaries such as scaffolding, temporary power, supervision and temporary accommodation will also have rates. On projects longer than around 18 months there might be escalation provisions based on annual percentage increases.
For more information see: Schedule of rates.
[edit] Summary
In summary, a bill of quantities will typically be used when a detailed design has been prepared and precise quantities can be calculated, whereas a schedule of rates will be used when quantities cannot be determined.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.