Difference between lump sum and measurement contracts
Lump sum and measurement are both types construction contracts.
Under a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. This is a type of 'fixed price' contract, where the contractors agree to execute the works described in the contract for a total sum of money (the contract sum). Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
For more information see: Lump sum contract.
NB it should be noted that whilst lump sum contracts are often referred to as 'fixed price', there are generally mechanisms within the contract to allow the contract sum to be changed, for example if variations are made, or if there are provisions to account for inflation. For more information see: Fixed price contracts.
Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) are generally used in situations where the design (or type of work required) can be described in reasonable detail, but the amount required cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
Measurement contracts can allow an early start on site, before design is complete, and they can allow changes to be made to the works relatively easily. However, there is inevitably some risk for the client as the cost of the works is not known. In effect, the client is taking the risk for any ‘unknowns’, and whilst this can result in competitive prices from contractors, the level of uncertainty for the client means that measurement contracts are rare other than on civil engineering projects.
For more information see: Measurement contract.
[edit] Related articles on Designing Buildings
- Construction contract.
- Contract sum.
- The difference between admeasurement and construction management contracts.
- Fixed price contract.
- Lump sum contract.
- Lump sum contract - pros and cons.
- Measured term contract.
- Measurement contract.
- Procurement route.
- Remeasurement.
- Right to payment.
- Schedule of rates.
- Schedule of rates term contract.
Featured articles and news
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese as well as English.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.