The difference between admeasurement and construction management contracts
The main differences between an admeasurement contract and construction management, are that the former is primarily for civil engineering projects. In both approaches a level of price uncertainty exists, in the latter though this price uncertainty can be clarified once the design is finalised and all contracts established, whereas the former is more open to the risk of cost quantities of work carried out differing from the quantities originally anticipated.
Admeasurement contracts are commonly used on civil engineering projects. Rates are provided in the contractor’s tender, either as part of the priced bill of quantities, or within a schedule of rates. Then the actual quantities of work carried out are measured and the rates are applied to those quantities. As a result, the quantities paid for may vary from the original estimate. The term ‘admeasurement’ is thought to have originated in the ICE Conditions of Contract measurement clauses, where it referred to establishing the difference between the final quantity of work carried out and the quantity originally anticipated.
Construction management is a procurement route in which the works are constructed by a number of different trade contractors, these trade contractors are contracted to the client but managed by a construction manager. The construction manager acts as an agent for the client, administering and co-ordinating the works contracts. A construction manager is generally appointed early in the design process so that their experience can be used to improve the buildability and packaging of proposals as they develop. Appointing a construction manager enables some trade packages to be tendered earlier than others, and sometimes, even before the design is completed. This can shorten the time taken to complete the project, however, it means that there will be price uncertainty until the design is complete and all contracts have been let.
[edit] Related articles on Designing Buildings
- Admeasurement.
- Bill of quantities.
- Consequential loss.
- Construction management.
- Contract conditions.
- Contract sum.
- Defined provisional sum.
- Difference between preliminaries and preambles.
- Extension of time.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Provisional sum.
- The difference between a prime cost sum and a provisional sum.
- Undefined provisional sum.
- Variations.
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.