Taking off construction works
The term ‘taking off’ refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
These elements can then be measured in number, length, area, volume, weight or time then collated and structured to produce an unpriced bill of quantities. This process is sometimes referred to as ‘working up’.
Where there may be uncertainty about some elements, they may be entered onto a query sheet that can be issued to the appropriate members of the consultant team for clarification.
The unpriced bill of quantities will have price and rate columns for tenderers to complete.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
Best practice for the preparation of bills of quantities is set out in the New Rules of Measurement (NRM) published by the Royal Institute of Chartered Surveyors and replacing Standard Method of Measurement, seventh edition (SMM7). Adopting the New Rules of Measurement means that all projects are taken off in the same way and in the same order following consistent rules.
Increasingly, software packages are available to assist in the preparation of preparation of bills of quantities, and building information modelling systems can be used to produce bills of quantities from information already contained within the model. The process in Building Information Modelling (BIM) is often referred to as material or quantity takeoff, which uses the underlying 3D parametric model to calculate materials takeoff for cost estimation, as well as in some cases embodied carbon calculations by adding the density factor and CO2 e per kg or volume of material.
In this process care must be taken that digital models are a fair representation of the actual product or component, for examples metal window frames being modelled as hollow extrusions rather than solid elements, the later can impact the material take-off dramatically increasing for example the assumed aluminium used by weight.
Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work, the contractor can be expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities' instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and to calculate the quantities that will be required.
For more information, see How to take off construction works.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Approximate quantities cost plan.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Computers in tendering.
- Construction work packaging.
- Contract documents
- Cost plans.
- Elemental cost plan.
- Extra over (EO).
- How to take off construction works.
- Measured quantity.
- New Rules of Measurement.
- Spot items.
- Standard Method of Measurement (SMM7).
- Tender.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
There is a detailed description of the traditional paper-based technique here: https://www.designingbuildings.co.uk/wiki/How_to_take_off_construction_works