Types of bill of quantities
Contents |
[edit] Introduction
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor) that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers for them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are two types of bill of quantities; firm and approximate.
[edit] Firm bill of quantities
A firm bill of quantities is used to obtain a lump-sum price for a fully-designed project. The work required is measured and described precisely, meaning that it can be priced accurately. As a result, tender prices should be reliable and good financial control should be possible. Where changes are necessary to the works described in the tender documents, the bill of quantities provides a good basis for assessing the costs of those changes.
[edit] Approximate bill of quantities
An approximate bill of quantities (sometimes referred to as a notional bill of quantities or provisional bill of quantities) is subject to re-measurement, and is used if there is insufficient information to prepare a firm bill of quantities at the tender stage, or if it is decided that a firm bill of quantities is not necessary.
The description of the works required is complete, but the quantities are approximate. As a result, quantified schedule of rates are provided by tenders rather than a lump-sum price, and the quantities are subject to re-measurement on completion.
This may appear an attractive option, as less cost and time is required to prepare the bill of quantities, however, typically, there will be more variations, and as re-measurement is required, overall administrative costs may be higher. In addition, there is greater cost uncertainty.
See also: Bill of quantities breakdown structures for descriptions of the three main breakdown structures for bills of quantities:
NB: An 'unpriced bill of quantities' (sometimes referred to as the tender pricing document) is the document issued to tenderers, who will then estimate their price for each item. The 'priced bill of quantities' constitutes the tenderer's offer and is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Without quantities.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.