Bill of quantities breakdown structures BQBS
Contents |
[edit] Introduction
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor) that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers for them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities (BQBS), each with advantages and disadvantages. If preparation of the bill of quantities is digitised according to a standard codification, it may be possible to re-order it from one structure to another.
[edit] Elemental
Measurement and description is undertaken by group elements, with each group element forming a separate section of the bill of quantities, irrespective of the order of work sections in NRM 2. Group elements are sub-divided through the use of elements, which are further sub-divided by sub-elements, as defined by NRM 1: Order of cost estimating and cost planning for capital building works.
This structure can make it easier for the cost consultant to analyse contractors' tender prices and collect real-time cost data.
For more information see: Elemental bill of quantities.
[edit] Work section
Measurement and description is divided into the work sections listed in NRM 2.
This structure may be preferred by contractors, as similar products and components are grouped together, rather than being spread across a number of different elements as they are in an elemental breakdown. This can make pricing easier for contractors.
For more information see: Work section bill of quantities.
[edit] Work package
Measurement and description is divided into employer, quantity surveyor or contractor defined work packages (based either on a specific-trade, or a single package comprising a number of different trades). This structure may be preferred by contractors for procuring from their supply chain.
For more information see: Work package bill of quantities.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Product breakdown structure.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Work breakdown structure.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
Registered building inspectors
Building types and conflicts of interest updates explaineed.
Engineering services still struggle with labour shortages
According to latest quarterly services survey of the sector.
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.