Managing the risks of state events following the Queen’s death
[edit] Current position?
With the passing of HM Queen Elizabeth II, a large majority of individuals and businesses are having to grapple with the unprecedented event of the death of a monarch.
The UK is currently in a period of mourning and with 19 September 2022, the day of the state funeral, having been declared a national bank holiday, questions have arisen as to the potential cascading effects that may permeate through the construction industry during this period.
The Department for Business, Energy & Industrial Strategy has given notice of the upcoming bank holiday and has stated there will be no statutory entitlement to time off, leaving it as a discretionary matter ‘for discussion between individuals and their employer’.
[edit] What are the contractual implications?
ECA Members are encouraged to talk to employers and clients and to check their contracts to ascertain whether they will have a right to time and money due to any potential disruption or delay caused by the state funeral and other ancillary arrangements which may disrupt project delivery.
The obvious implications of a declared bank holiday are that it may give rise to a worker expectation that where the day is worked, workers should receive additional remuneration to compensate for the loss of a bank holiday. Members will need to factor this into the management of their business and project management administration and cost considerations.
As parties may have entered into bespoke contractual arrangements an entitlement to time and money will be dependant upon the provisions of each individual contract. However, there are some general points our Members should take into consideration.
If an employer/main contractor expressly instructs work to stop on site on the day of the bank holiday, for example in order to allow employees to attend the state funeral or to not have loud machinery in use on site out of respect during the bank holiday, then Members will have a strong case to argue that such an instruction constitutes a variation/change under the contract and therefore a Member (who is a sub-contractor) should be able to claim for time and loss & expense/compensation. These are covered under relevant events under the JCT suite of contracts (clauses 2.23 to 2.26 of the JCT D&B and clauses 2.26 to 2.29 of the JCT SBC) and under compensation events for the NEC 3 and NEC 4 ECC (section 6).
On the other hand, if an employer/main contractor does not issue any specific instructions for work to cease on site and, for example, leaves the option to pay respects to the discretion of the supply chain, then Members which the supply chain must be prepared to play catch up, as it will be more difficult to prove an entitlement to time and money if Members choose to forego a day’s productivity as this is unlikely to amount to a relevant event or a compensation event.
In such an instance, we would advise Members to weigh up the commercial risks of falling slightly behind on a project and having to catch up, against the decision to allow their workforce the opportunity to pay their respects on a day of national mourning.
Regardless, Members should factor-in the requirements to issue appropriate notices (via the notice requirements) for; extension of time, loss & expense, early warning and compensation vent as may be required by the contract. If you don’t operate the machinery, you can’t claim an entitlement.
We would encourage our Members to maintain an open line of communication with employers/main contractors during these times as this is an unprecedented event and there is an industry wide push for collaboration between parties.
If we have learnt anything from Covid-19, it is that clear dialogue and record keeping regarding arrangements, expectations, float, programme and cost implications will give parties the best opportunity to appropriately allocate risk and ensure that any contractual mechanisms in place are followed. This should minimise delay and disruption and ensure Members are compensated.
Members may also want to consider that where ‘dayworks’ are a contractually valid method of valuing variations or changes, these will be inherently linked to the unionised wage rates calculated on the basis of 8 public holidays in an ordinary year. This year we have had 9 bank holidays due to the Platinum Jubilee, and if the state funeral is declared by the relevant sector agreement to be an additional bank holiday it will introduce a 10th bank holiday, leading to a potential further loss of productivity and increasing the resulting costs of employers.
The proximity of the 19th of September, under a best-guess scenario is likely to see an additional days’ leave granted at normal wage rates to be used either on the 19th or before the end of 2022 at the employer’s discretion.
Member companies who are part of the JIB are advised to check the JIB website in the week leading up to the state funeral to seek confirmation of the agreed position. Non JIB Members will have discretion to enter into daywork rates negotiation and will have the option to adopt the JIB model should they wish to do so.
This article originally appeared under the same title on the ECA news and blog site, it was written by Obaid Bin-Nasir, Legal and Commercial Advisor ECA dated September 14, 2022.
--ECA
[edit] Related articles on Designing Buildings
Featured articles and news
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.