Furniture fixtures and equipment FF&E
FF&E refers to the procurement of furniture, fixtures and equipment.
This might be procured separately to the main construction contract (or elements of them), particularly by clients that already have systems in place for procuring fixed and loose furniture, fittings and equipment; for example schools, universities, or hospitals.
It is very important under such circumstances to define very clearly which contract every element of FF&E is within (for example, there may still be unusual or large items that it may be more sensible to procure under the main contract).
It is also important to ensure that any building work required for the installation of such items is identified and procured, that any services required (such as power or drainage) are identified and that the installation of FF&E is properly integrated into the main contract.
Requirements that affect the main contract might include:
- Built-in equipment requiring mechanical or electrical connections, such as fume cupboards or drinks stations. A description of built-in equipment should include; location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Built-in equipment that does not require services such as cupboards or shelving. These should be described in terms of their location and size.
- Stand-alone loose furniture and equipment requiring services, such as washing machines, coffee machines and scanning equipment in hospitals. These should be described in terms of their location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Stand-alone loose furniture and equipment not requiring services such as tables and chairs. These should be described in terms of their location and size.
It is also important that any elements that are outside of the main contract are included in the client's cost plans.
FF&E can be procured from specialist suppliers, or suppliers with whom the client already has a long term relationship. This may include maintenance arrangements. Some elements may be specially designed by FF&E designers or sourced by FF&E consultants. There is also a need for a carefully managed FF&E inventory and logistical planning to ensure items are available on-site at the right time.
In managing the procurement of FF&E, consultants take on the complicated and time-consuming task of coordinating with the design team, external vendors and internal departments for the following:
- Programming and planning.
- Sourcing.
- Project procurement strategy and risk analysis.
- Request for proposal (RFP) document development.
- RFP process management.
- Contract negotiation and buy-out.
- Order expediting and tracking.
- Installation, product acceptance and close-out.
For more information, see FF&E consultant.
[edit] Related articles in Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.