Request for proposals from consultants RFP
The process of selecting consultants might involve the preparation by the client of a 'request for proposals' (RFP) which is sent out to each prospective consultant. Consultants respond by submitting 'consultant's proposals' to the client.
The request for proposals describes the nature of the project, the nature of the appointment and a description of the information required from the consultant.
The request for proposals might include:
- The strategic brief.
- The management structure.
- The scope of consultant services required and how fees should be quoted and broken down against stages of the project.
- The project programme.
- The construction budget (without contingencies and VAT).
- The intended method of procurement (or a request for options if the procurement route has not been chosen yet).
- The form of agreement and conditions of engagement (such as step-in rights, warranties, a model enabling amendment making a BIM protocol part of the contract documents, and so on).
- The level of professional indemnity insurance required.
- The selection criteria that will be used.
- The procedure that will be followed.
- If building information modelling (BIM) is being used, the Employer's Information Requirements (EIR).
- Targets for post-occupancy evaluation.
It might request consultant's proposals including:
- A list of key personnel to be allocated to the project, their role in the project, CVs of staff and a description of relevant experience on similar projects.
- Hourly rates to be applied to any work outside the proposed scope of services.
- Identification of any sub-consultants the candidate intends to use.
- A broken-down payment and resource schedule with trigger dates against work stages.
- Evidence of professional indemnity insurance.
- If BIM is being used, a BIM execution plan.
- A list of recently completed commissions with referees and detailed of other consultants involved.
- A statement of design intent based on the brief.
If the request for proposals involves significant design work from the consultant, it is good practice for the client to offer payment for the work involved in preparing these designs. This will encourage the consultant to prepare their proposal more carefully, and will also demonstrate to them that the client is serious about the project and is likely to treat them fairly.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Architect's fees.
- Automated vendor selection.
- Budget.
- Building information modelling.
- Collaborative practices.
- Consultant team.
- Consultant team start up meeting.
- Consultant's proposals.
- Design liability.
- Employer's information requirements.
- Employer's requirements.
- Fees.
- Fee proposals.
- Management structure.
- Procurement route.
- Professional indemnity insurance.
- Project programme.
- Proposals.
- RFx.
- Schedule of services.
- Strategic brief
Featured articles and news
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Installing solar panels on listed structures.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.
ECA learning zone and industry focus video series
From updates and amendments to circular economy, emergency lighting and much more.