Exclusion grounds under the Single Procurement Document (Scotland)
Contents |
[edit] Introduction
The Single Procurement Document (Scotland) - also referred to as SPD (Scotland) - is a document that contains questions used at the selection stage for post-Brexit procurement exercises in Scotland. It is used to identify suitably qualified and experienced bidders for public sector procurement in Scotland.
The Procurement Journey portion of the Scottish Government’s procurement guidance website offers guidance for public sector buyers who procure goods, services and care and support services under SPD (Scotland).
[edit] Route 3
Procurement officers involved in high value or complex purchases (typically of, or more than £50,000 excluding VAT for goods and services) should follow the guidance offered in Route 3 of the Procurement Journey. This includes strict procedures and rules, including circumstances in which a bidder must be excluded from the procurement process. This is known as a mandatory exclusion ground. There are other circumstances in which a bidder may be excluded on a case by case basis. These are known as discretionary exclusion grounds.
All exclusion criteria must be relevant and proportionate to the subject matter of the contract.
[edit] Determining the parameters of exclusion
The exclusion process involves evaluating whether the bidder has committed any offences.
There are two types of questions that can be asked when determining whether or not there are grounds for exclusion questions:
- Mandatory exclusions. The buyer must ask questions regarding these exclusions and the bidder may be excluded from the procurement process if specified offences have been committed and the self-cleansing measures taken are not sufficient to demonstrate reliability. Examples of such instances might include corruption, bribery, money laundering or certain types of fraud. They may also include tax and social security obligations (binding decision - judicial or administrative).
- Discretionary exclusion. The buyer may ask questions concerning these exclusions and the bidder may be excluded from the procurement process if they have taken part in certain activities and the self-cleansing measures taken are not sufficient to demonstrate reliability. These should be considered on a case by case basis by the buying organisation. Examples of such instances might include social, environmental and labour laws or obligations, bankruptcy or insolvent businesses, incidents of grave professional misconduct, conflicts of interest, distortion of competition and contract deficiencies, or misrepresentation or undue influence. They may also include tax and social security obligations (decision by means other than a binding judicial or administrative decision).
In either mandatory or discretionary exclusion grounds based on tax and social security breaches, the bidder should not be excluded if they have fulfilled their obligations by paying or entered into a binding agreement with the view to paying monies due or the obligation to repay otherwise ceases.
[edit] What is self cleansing?
According to the Construction Procurment Handbook Glossary, self cleansing is: ‘The process by which candidates which have been excluded from a procurement process can demonstrate that they have taken action to remedy and areas which were the cause of their exclusion.’
As part of the self cleansing process, the bidder must satisfy that it has:
- Paid, or undertaken to pay, compensation for any damage caused by the criminal offence or misconduct.
- Provided detailed facts and circumstances by collaborating with the investigating authorities.
- Taken appropriate concrete technical, organisational and personnel measures to prevent further criminal offences or misconduct.
[edit] Extenuating circumstances
In exceptional circumstances, it may be possible to disregard the mandatory exclusion grounds when selecting a bidder. This can only be done where there are overriding reasons relating to the public interest. This provision is known as derogation from the mandatory exclusion considerations.
This allows buying organisations to respond to unforeseen emergency circumstances. An example may be where urgently needed emergency equipment can only be purchased from a bidder to whom one of the mandatory exclusion grounds otherwise applies.
[edit] Related articles
- Dynamic purchasing system under the Single Procurement Document (Scotland).
- Procurement route.
- Public procurement.
- Self-cleanse.
- Single Procurement Document (Scotland).
- Tender processes for construction contracts.
- Typical tender process for construction projects.
- Unfair contract terms act.
[edit] External resources
- Scottish Government, Construction Procurement Handbook, Glossary.
- Scottish Government, Procurement Journey, Exclusion criteria.
- Scottich Government, Procurement Journey, Route 3 Introduction.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.