Cost overruns in construction
In construction, cost overruns are relatively common, occurring when the costs being incurred are in excess of the amounts that have been budgeted for.
There are a number of possible reasons for this:
- Construction contracts are often tendered and won on the basis of the lowest cost bid. Costs can then increase as contractors attempt to claw back some profit.
- Construction projects are complex, involving a large number of different parties, components, requirements and other factors.
- Projects can take a long time to complete, during which costs may change.
- Deficiencies and inaccuracies in design.
- Poor project management.
- Changes in client requirements.
- Unforeseen costs that only become apparent as the works progress.
- Poor communication between project team members.
- Tools, equipment and plant being unavailable, in poor condition, etc.
- Skilled workers being unavailable.
- Inaccurate cost information that leads to incorrect pricing (e.g. material prices).
- Adverse site or ground conditions.
- Late or withheld payments.
- Scope creep.
The different ways in which cost overrun can be described include:
- As a percentage of the total cost.
- As a total percentage including the original budget and the overrun amount.
- As a percentage of the cost overruns to the original budget.
In order to address and manage cost overruns, it is important to identify what the root causes are. While specific events such as extreme weather conditions can cause delays or damage which may result in cost overruns, they are often the result of more complex project management issues that can be difficult to untangle.
The largest cost overruns tend to occur due to a change in requirements. If, for example, the client needs a space to be 20% larger than originally anticipated, then the cost is likely to increase by at least 20%. It is very important therefore to ensure that the project brief is comprehensive and that all project stakeholders accept it and agree on the specific scope of work and performance requirements.
Pre-construction estimates and careful project planning are then vital in terms of ensuring accuracy and confidence in the project costings, particularly if the project is complex and has the potential to change.
Design and construction issues can be mitigated in some cases by using project-wide project management, cost control software or building information modelling (BIM) as a way of ensuring all stakeholders are using the same up-to-date design information, as well as being able to make real-time adjustments.
Change orders may also be a reason for costs overrunning. A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original contract amount and/or completion date.
If one of the parties to a contract fails to perform as required by the contract, and this results in costs overrunning, it may constitute a breach of contract. A breach of contract may entitle the innocent party to make a claim for damages for the losses it has suffered.
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A call for prevention and sensitive re-use.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
BSA residential sector competence standards guidance
BSAS 01:2024 Organisational Capability Management System Standard - Competence Assurance.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.