[edit] What are transitional arrangements in building control?
Transitional arrangements allow projects to stay under the current building control regime – and avoid transfer to the Building Safety Regulator (BSR). Which means eligible projects can stay under the old rules.
[edit] How does a building qualify for transitional arrangements?
Developers must take the required steps for their projects to qualify.
If a project had building control arrangements established before October 1st, 2023, and has made substantial progress before April 6th, 2024, it qualifies for transitional provisions. A notice of sufficient progress must be given to the local authority in order to qualify
As such under these provisions, a project can continue to be regulated by the existing building control provider. This will require the building control provider to be appropriately registered with the BSR.
[edit] What is required for transitional arrangements?
In order to benefit from transitional arrangements, it is essential that notice is given to the relevant local authority, indicating that the building work has progressed sufficiently.
For the construction of a higher-risk buildings, sufficient progress means when pouring concrete for the permanent placement of foundations or piling has started. For work on existing buildings, this means when any work has begun. There is no specific rule for what counts as starting work, but it usually includes any significant building activity mentioned in the project application.
If the project involves an Approved Inspector (AI), a copy of this notice must also be goven to the AI as well. Failure to send notice to the local authority will result in the project transferring to the BSR.
Projects must use a suitably Registered Building Inspector (RBI) and suitable building control arrangements to continue benefitting from the transitional arrangements. Suitable building control arrangements means submitting full plans to the local authority. The plans must not be rejected. Or it means giving an initial notice to the local authority. The authority must accept the notice.
This article is based on the Government announcement "Eligibility for transitional arrangements in building control" updated March 11, 2024.
[edit] Related articles on Designing Buildings
- Building a safer future: proposals for reform of the building safety regulatory system.
- Building a Safer Future, Independent Review of Building Regulations and Fire Safety: Final Report.
- Building safety
- Building safety act 2022
- Building safety case.
- Building Safety Charter.
- Building safety certificate.
- Building safety in Wales.
- Building Safety Manager.
- Building Safety Regulator
- CIAT raises concerns about Building Safety Bill.
- CIOB reviews the Building Safety Bill.
- Competent person.
- Fire inspector.
- Fire Safety Act.
- Fire safety design.
- Fire Safety Order.
- Fire (Scotland) Act 2005.
- Golden thread.
- Grenfell articles.
- Hackitt Review.
- Health and safety for building design and construction.
- Health and safety plan.
- New Regulations published under Building Safety Act
- Reform of building safety standards.
- Risk assessment.
- Safety audit.
- Safety briefing.
- Safety management.
- The Building Safety Bill - A Quality Response.
- The Building Safety Bill and product testing.
- The Building Safety Bill, regulations and competence.
- The golden thread and BS 8644-1.
- What is a hazard?
- UK building control regime under the new Building Safety Act regulations
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.