Time certainty
Construction projects are often seen to be a balance between three related performance indicators; time, cost and quality. Generally, an increace in quality will result in an increase in cost and time, a reduction in time will result in an increase in cost and so on.
For clients and contractors in the construction industry, time certainty is one of the most important performance criteria.
Time certainty is the likelihood that even before a project starts, but also during the project, it will be completed within the required time. Time certainty is also affected by cost certainty which is the likelihood that a project will be completed within the budgetary requirements.
Construction clients often hold these two concepts as their top priorities as delays and cost overruns can lead to higher costs for the client and a possible diminished relationship between client, contractor, occupants, customers and so on. For contractors, an excessive time extension to the project programme may mean lower than expected profits and a diminution of reputation and competitiveness.
Construction projects tend to be high-risk undertakings which very frequently generate time and cost overruns. Typical factors that can delay a project include:
- Clients making sudden changes and introducing variations.
- Slow decision-making.
- Unforeseen ground conditions.
- Delays in material supply.
- Inclement weather.
- Disputes.
- Defects.
- Changes in market conditions.
A 1996 study by the Construction Industry Board (CIB) revealed that time certainty (and also cost certainty) is more often than not likely to be under the contractor’s control. This is mainly because time overruns are frequently seen to be:
- Symptomatic of poor management.
- The contractors’ inability to predict and control the time needed to complete a project.
- Inaccurate material estimating.
- Poor labour productivity.
- Inadequate planning.
- Poor site management.
If delays occur on a project, contractors are impacted almost immediately by additional costs resulting from:
- Increases in overheads.
- Hiring more operatives.
- Longer plant-hire periods.
- Storage of materials.
- Delayed payments from the client or penalties.
In their paper ‘Cost Certainty and Time Certainty: An International Investigation’ (Hong Xiao and David G Proverbs), time certainty was found to be largely dependent on first, cost certainty and second, the importance contractors allocate to cost, comparing them to the two sides of the same coin; neglecting one will have an adverse effect on the other. Also, the authors maintain that projects completed on time are those where the contractor realises there is no other option and so does as much as possible to bring this about.
Greater planning input by the contractor is also known to have a positive effect on improving project performance (Faniran et al., 2001) and is why faster projects are usually found to be cheaper at the tender stage, punctual to deadlines and completed to customers’ satisfaction (NEDO, 1988).
A possible indicator of a contractor’s time certainty is that delays on previous similar projects are likely to reoccur on future projects. A good reputation is therefore critical for time certainty performance.
Generally time certainty improves as a project progresses, as there are fewer remaining risks that could affect project completion.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works
- Adverse weather during construction
- Certificate of non completion
- Common refusals of extensions of time
- Completion date in construction contracts
- Concurrent delay
- Contract administrator for construction contracts
- Contractor delay.
- Defects in construction
- Delays on construction projects
- Extension of time - approval letter example
- Force majeure in construction
- How to prepare a claim for an extension of time
- Liquidated damages in construction contracts
- Loss and expense
- Nominated sub-contractor
- Octoesse LLP v Trak Special Projects Ltd
- Practical completion
- Prolongation in construction contracts
- Reasonable time.
- Relevant event
- Relevant events v relevant matters
- Relevant matters in construction contracts
- Time at large
- Variations in construction contracts
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.