Prolongation in construction contracts
As per the definition contained in the Society of Construction Law Delay and Disruption Protocol the term ‘prolongation’ refers to 'the extended duration of the works during which time-related costs are incurred as a result of a delay' - usually recognised as the additional projected time required to complete a contract extending beyond the contractual completion date.
Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party (usually the Employer). Such events might include; failing to give the contractor possession of the site on the date specified in the contract; delays in giving instructions, and so on.
The contractor may incur additional costs as a result of having to remain on site for longer than anticipated, for example, additional labour costs, plant costs, off-site overheads, fluctuations, and so on.
Prolongation is sometimes described as being synonymous with ‘loss and expense’, however, this is incorrect. Loss and expense is a wider term that refers to matters which are the responsibility of the client that materially affect the progress of the works. This includes matters that disrupt, rather than delay the progress of the works, but still entitle the contractor to make a claim for additional costs incurred. Claims for disruption result from the additional cost of adopting inefficient working methods as a result of the disruption.
For more information, see Disruption claims in construction.
Prolongation and disruption therefore are two separate elements that might result in a claim for loss and expense. The prolongation element is dependent on the completion date being delayed.
Depending on the terms of the construction contract, prolongation might relate to the project as a whole, or to a specific aspect of it.
Generally a disruption event is easier to prove than a critical delay prolongation event i.e. a failed critical delay prolongation claim will often be used as proof of disruption. However, prolongation costs are often considered easier to demonstrate than disruption costs.
For more information see: Loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February