Self-build home: project plan
This is a free-to-use, open-access plan for the organisation, design and construction of self-build homes.
If you have ideas for things to add to the plan, you can either edit the plan and add them yourself, or submit a comment and we will add them for you.
There are a number of delivery routes for self-build homes:
- Purchase a kit house.
- Appoint a design and build contractor to design and build the home.
- Appoint consultants to design the home then get a contractor to build it.
- Appoint consultants to design the home then manage the construction yourself.
It may not be clear which route should be followed until initial assessments have been carried out, a plot located and a brief prepared. See: Develop a delivery strategy for more information.
It is also possible to work with other organisations such as social landlords, developers, or community groups to develop a self-build home, however, these projects are likely to follow a plan imposed by the lead organisation and so they are not covered here, although many of the project stages will be similar. Working with a developer is sometimes called ‘custom build’ rather than ‘self build’.
See Custom-build home for more information.
An outline project plan is presented below. It describes activities step-by-step from the first moment it becomes apparent a self-build home could be a possibility right through to occupation of the completed building. Most of the stages are common to all four self-build routes, but the appointment stages vary.
Clicking on any of the stages will take you to a detailed description of the tasks that need to be carried out.
Stage 1: Justify the project.
Stage 2: Prepare a brief.
Stage 3: Find a plot.
Stage 4: Develop a delivery strategy.
Stage 5: Raise finance.
Stage 6: Acquire the plot.
Stage 7: Appoint designers.
- Appoint consultants to design the home, or;
- Appoint a contractor to design the home, or;
- Appoint a supplier to design a kit house.
Stage 8: Prepare a concept design.
Stage 9: Submit a planning application.
Stage 10: Prepare a detailed design.
Stage 11: Submit a building regulations application.
Stage 12: Prepare production information.
Stage 13: Appoint contractors.
- Appoint a contractor to construct the home, or;
- Appoint a range of contractors and suppliers to construct the home, or;
- Confirm appointment of the design and build contractor to construct the home, or;
- Confirm appointment of the supplier to fabricate and install the kit house.
Stage 14: Prepare for construction.
Stage 16: Construction.
Stage 17: Occupy the home and rectify any defects.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments
It seems that the handover information such as building manual, H&S files, and other operation and maintenance documents are not mentioned here.
Not surpised that most building owners do not know what is in their building.