Self-build home: Construction
Introduction.
The construction stage is the process of constructing the works described in the design drawings and specifications. At the end of the stage, the self-build home should be ready for occupation, although the contractor may be required to return to the site, even after occupation, to rectify any defects that appear.
Depending on the procurement route that has been adopted, tasks in this stage, may be undertaken by the self builder, the contractor(s), consultants or the kit-house supplier.
Throughout this stage, it may be necessary to procure items outside of the construction contract that will be required to occupy the home, such as; furniture, kitchen equipment, ICT equipment and so on.
Be aware that whilst self-build clients are ‘domestic clients’ for the purposes of the Construction (Design and Management) Regulations, they can attract health and safety duties under Part 4 of the regulations if they control the way in which construction work is carried out. See CDM for self-builders and domestic clients for more information.
- Ensure site induction talks are carried out, explaining key safety issues and site organisation.
- Introduce a signing in and signing out book for all personnel.
- When appropriate, issue notices for each trade contractor to commence work on site along with instructions regarding phasing and sequencing of the work.
- Co-ordinate the preparation of any additional information required by the trade contractors for construction.
- Where there are proposed variations to the agreed works the self builder should give careful consideration to costs that may be incurred and should assess any alternative options.
- Regular inspections should be carried out and progress photos taken. In particular, photograph defective work before any remedial works are carried out and record the date the photos were taken.
- There should be regular construction progress meetings to assess progress against the programme, resolve design issues, inspect samples, and discuss the organisation of the next stage of the construction works.
- It is important to keep all contractors and suppliers informed about the progress of the project so they are able to plan their manufacture and installation works before receiving a notice to commence work. They will have a number of clients to satisfy and are likely to favour those that allow them to maximise their efficiency.
- Visit major supplier’s factories to check work is in progress and products are as ordered.
- Regular payments must be made to contractor(s) in accordance with the requirements of the contract.
- Throughout the project gather any product literature supplied with goods. File these in preparation for creating an operation and maintenance manual.
- Co-ordinate the utility companies to install meters and connect the permanent services.
- As the construction nears completion, agree procedures for inspections, commissioning, and testing building services.
- Ensure contractor(s) rectify any defects that become apparent during commissioning, testing and inspection procedures.
- Arrange for final inspection of the works by the building control inspector (or approved inspector) and arrange for them to issue a building regulations completion certificate.
- If the works (or trade contracts) are complete, certify practical completion. See practical completion for more information.
- Make any payments due.
- Inform insurers of completion.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.