Self-build home: Prepare a detailed design
Introduction.
In this stage, we attribute design activities to ‘designers’. These may be architects and engineers, a design and build contractor, or a kit house supplier. If a kit house supplier is only supplying the house itself, additional design consultants may be required.
The detailed design process takes on and develops the agreed concept design. By the end of the detailed design stage the design should describe all the main components of the building and how they fit together, but the works will not yet have been defined in packages to obtain prices for construction. Detailed design should provide sufficient information to make building regulations applications.
The designer should co-ordinate consultations about the functional aspects of the detailed design with the self builder and should also co-ordinate consultations with the building control body. This may result in amendments to the design.
An elemental cost plan and cash flow projection should be prepared.
During the detailed design stage the designers may require input from the suppliers of goods and services that will be used in the construction of the building. It is important to ensure that pricing and contract conditions have been settled with these companies before any commitment to use their services is made, or it should be made clear that there is no commitment to use them for construction.
The designer will co-ordinate the incorporation of designs by specialist suppliers or contractors into the overall design and will source necessary samples of materials, components and assemblies for approval by the self builder. It may be appropriate to arrange visits to the specialist contractors' and suppliers’ premises to assess samples or mock-ups and to witness tests.
At the end of the stage, the designer should submit a full set of project drawings, specifications and a cost plan to the self builder for comment and approval before progressing to the next stage. For a full description of the aspects of design that might be developed during this stage, see Detailed design.
NB where the proposed development affects a party wall or party structure, it may be appropriate to issue party wall notices and to appoint party wall surveyors at this stage.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.