Dayworks in construction
Daywork is a means by which a contractor is paid for specifically instructed work on the basis of the cost of labour, materials and plant plus a mark up for overheads and profit. It is generally used when work cannot be priced in the normal way.
NRM2, RICS new rules of measurement, Detailed measurement for building work defines daywork as; '... the method of valuing work on the basis of time spent by the contractor’s workpeople, the materials used and the plant employed.'
Examples of when daywork may be applied are when unforeseen obstructions are encountered during ground works or when work is instructed for which there are no comparative rates in a bill of quantities.
It is usual for most contracts to contain clauses that provide a method of evaluating variations, additional work and instructions by using existing contract rates and prices. NEC contracts favour pre-agreed sums based on acceptance of a contractor’s quotation.
There are two basic options as to how daywork rates can be priced:
Option A – a percentage addition
- Prime cost to which a percentage is added for overheads, profit and incidental costs.
Option B – all inclusive rates
- All inclusive rates are quoted at tender and incorporated in the contract documents. These include an allowance for overheads and profit, either fixed for the period of the contract, or, in the case of contract conditions that are index linked, subject to an inflation allowance.
[edit] Related articles on Designing Buildings
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments
There is a great mobile phone App that lets you quickly create a daywork or just a resource estimate and send it to the office in minutes, the App date stamps start and finish photos to help you prove the record is a true reflection of the works. It also allows you to quickly get pre-authorisation of the daywork prior to starting the works. Here's the link http://www.constructionrates.co.uk/Rate_Gen/Android_Mobile_Tablet_Smart_Phone_Daywork_App_UK_Construction_Industry.htm