Taking off construction works
The term ‘taking off’ refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
These elements can then be measured in number, length, area, volume, weight or time then collated and structured to produce an unpriced bill of quantities. This process is sometimes referred to as ‘working up’.
Where there may be uncertainty about some elements, they may be entered onto a query sheet that can be issued to the appropriate members of the consultant team for clarification.
The unpriced bill of quantities will have price and rate columns for tenderers to complete.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
Best practice for the preparation of bills of quantities is set out in the New Rules of Measurement (NRM) published by the Royal Institute of Chartered Surveyors and replacing Standard Method of Measurement, seventh edition (SMM7). Adopting the New Rules of Measurement means that all projects are taken off in the same way and in the same order following consistent rules.
Increasingly, software packages are available to assist in the preparation of preparation of bills of quantities, and building information modelling systems can be used to produce bills of quantities from information already contained within the model. The process in Building Information Modelling (BIM) is often referred to as material or quantity takeoff, which uses the underlying 3D parametric model to calculate materials takeoff for cost estimation, as well as in some cases embodied carbon calculations by adding the density factor and CO2 e per kg or volume of material.
In this process care must be taken that digital models are a fair representation of the actual product or component, for examples metal window frames being modelled as hollow extrusions rather than solid elements, the later can impact the material take-off dramatically increasing for example the assumed aluminium used by weight.
Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work, the contractor can be expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities' instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and to calculate the quantities that will be required.
For more information, see How to take off construction works.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Approximate quantities cost plan.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Computers in tendering.
- Construction work packaging.
- Contract documents
- Cost plans.
- Elemental cost plan.
- Extra over (EO).
- How to take off construction works.
- Measured quantity.
- New Rules of Measurement.
- Spot items.
- Standard Method of Measurement (SMM7).
- Tender.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
There is a detailed description of the traditional paper-based technique here: https://www.designingbuildings.co.uk/wiki/How_to_take_off_construction_works