Construction work packaging
Contents |
[edit] Introduction
Packaging is normally associated with general contractors who split a large project into a series of work packages suitable for obtaining tenders and placing orders with the subcontracting and goods supply chain, thereby transferring risk for delivering some elements of the works to others.
However, the design team, generally advised by the cost consultant, may elect to preempt a general contractor by selecting specialist systems required for early inclusion into the evolving design. This creates a built in package requirement.
A package can include any or all of the following activities:
- Design/engineering.
- Manufacture and/or supply.
- Pre-fabrication and delivery.
- Site installation.
- Operation and maintenance.
[edit] Package contracts
The conditions of the package contract will vary depending on the main contract arrangements.
Under a traditional contract the main contractor will split tender documents into subcontractor packages that are geared to the most competitive returns, which are then included in the main contractor’s tender offer to the client.
Under a management contract the client’s cost consultant and the management contractor, in co-operation with designers, decide how to package the works and direct the team as a whole to produce package designs suitable for obtaining subcontracts under the terms of the management contract. This method of procurement allows parallel working on design and construction. For example, work on the foundations and superstructure can commence before the design for the whole building is complete.
A construction management contract follows the procedure of a management contract except the package contractor enters into a direct contract with the client, administered by the construction manager.
The adoption of Building Information Modelling (BIM) is likely to lead to an increase in the early appointment of specialist package contractors by design teams to avoid having their model unravelled by appointments that might otherwise have been made at a later stage. This suggests that in traditional tendering, main contractors will be forced to adopt the specialist without any freedom of choice. This may lead to some interesting legal wrangles in respect of non-performance or delays caused by the imposed specialist subcontractor.
[edit] Package definition
For contractors to successfully transfer risk for elements of the works there are a numbers of issues to consider:
- The interface between packages must be carefully considered, defined and constantly monitored.
- Elements can fall between packages (for example the flashing to a roof rainwater outlet).
- Responsibility and consequent liability must be clearly defined.
- The way each package is to be monitored should be agreed when placing orders to save package management resources and avoid man-for-man marking which is duplicative and costly.
- The risks transferred to the package contractor need to be proportionate to the size of organisation executing the package. For instance four weeks of full liquidated and ascertained damages might be of greater value than the subcontractor’s annual turnover and so would be unsustainable.
If the project is split down into too many packages it becomes confusing and unmanageable. As a very general rule of thumb the following might apply:
- On large building projects divide the project cost by £2m to establish the number of differently priced packages. For example; £200m = 100 packages, £50m = 25 packages, and so on.
- On medium size building projects divide the project cost by £1m to establish the number of differently priced packages.
- On fit out projects, which have a high monthly turnover and a fast programme, stick to say five packages; mechanical, electrical, information technology, building work and furniture and equipment.
[edit] Typical breakdown of packages (excluding preliminaries) on an office development
- Demolition and site clearance.
- Piling.
- Substructure and underground drainage.
- Superstructure.
- Cladding system.
- Roof and balcony finishes.
- Floor and staircase screeds.
- Mechanical installations and plumbing.
- Electrical installation.
- Raised access floors.
- Suspended ceilings.
- Metalwork and balustrades.
- Brick and blockwork.
- Prefabricated toilets.
- Internal partitions.
- Joinery and ironmongery.
- External works.
- Decoration.
- Testing and commissioning.
- General building work including plastering.
[edit] Association for Project Management definition
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests work packages are: ‘…the lowest level at which performance data is normally analysed. It is therefore important to balance the length and scope of the work package against reporting cycle lengths, and to consider when and how to earn ‘value’. Each work package must have a clearly defined start condition and finish point, with all deliverables defined. The scope of each work package must be unambiguously defined with the procedures to be followed identified. Each work package comprises a number of activities to be performed.’
See also: Planning package.
[edit] Related articles on Designing Buildings
- Bills of quantities.
- Common arrangement of work sections.
- Comparison of SMM7 with NRM2.
- New Rules of Measurement.
- Package contractor.
- Package tie-in.
- Planning package.
- Preliminaries.
- Production information.
- Standard Method of Measurement (SMM7).
- Work breakdown structure.
- Work component.
- Work package contractor.
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Comments
Nice post and informative content. Thank you so much for sharing this post. For more information visit here: https://www.behance.net/TimElsea