Single-stage tender
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services.
Tender procedures will vary depending on the nature of the goods or services that are being procured, but very broadly they can be classified as either single-stage or two-stage.
Single-stage tendering is the more traditional route, used when all the information necessary to calculate a realistic price is available when tendering commences:
- An invitation to tender is issued to prospective suppliers (perhaps following completion of a pre-qualification questionnaire and/or a pre-tender interview). The invitation to tender will include information describing the goods or services required in sufficient detail to enable prospective suppliers to prepare an accurate tender.
- Tenders are prepared and returned by prospective suppliers (this may involve questions and answers and a mid-tender interview to clarify the client’s requirements).
- Submitted tenders are then assessed and compared (this may involve further interviews).
- The preferred tenderer is selected and negotiations opened.
- Subject to the outcome of those negotiations the preferred tenderer may then be appointed.
See Tender for more information.
However, increasingly it is becoming useful to obtain input from prospective tenderers before there is sufficient information available for the main contract to be awarded. This can allow early input from the main contractor, or early appointment of a specialist contractor, such as a cladding contractor, before the main contract has been awarded.
A two-stage tender process may also be adopted on a design and build project where the employer's requirements are not sufficiently well developed for the contractor to be able to calculate a realistic price. In this case, the contractor will tender a fee for designing the building along with a schedule of rates that can be used to establish the construction price for the second-stage tender.
See Two-stage tender for more information.
Two-stage tendering enables the client to transfer design risk to the contractor, but the client inevitably loses leverage as the contractor becomes embedded in the team and competition is less of a threat. However, whilst tender prices for two-stage contracts may initially be higher than single-stage tenders, which are subject to full competition, the final account tends to include fewer variations and fewer claims.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.