Public project: occupation and defects liability period
The occupation and defects liability period follows practical completion. It is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed (although on some projects, the integrated supply team may go on to operate the development). As the development is now occupied, close co-operation is required between the integrated supply team and the client so as so not to disturb occupants.
Depending on how experienced the client is, they may appoint external consultants to assist them. This means that some of the tasks attributed to the client below might actually be carried out by independent client advisers, a project manager or a contract administrator (employer's agent on design and build projects) and vice versa.
[edit] Starting the work stage.
The integrated supply team arranges a start-up meeting to plan the work stage.
The client may identify a requirement to appoint additional independent client advisers.
[edit] Rectifying defects.
We attribute contract administration tasks (such as making payments under the construction contract) to a contract administrator. Under some forms of procurement (such as design and build) the contract administrator (sometimes referred to as the employer's agent) will work for the client, however, on private finance initiative (PFI) projects, the client will not be a party to the construction contract and will not make payments for construction. Instead, the body funding the integrated supply team (perhaps a special purpose vehicle (SPV)) will take on the role of client for the construction contract and so they may appoint the contract administrator.
If the contract allows, the contract administrator may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the contract administrator (or integrated supply team). On large projects the integrated supply team may set up a hot desk for responding to any complaints or provide assistance required by the incoming occupants. The integrated supply team and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to co-ordinate amendments to the health and safety file.
If any amounts are due to the integrated supply team, they prepare interim applications for payment. The contract administrator checks applications for payment and issues interim certificates (payment notices).The notices must be issued within five days of the dates for payment set out in the contract. If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client (or funder) makes interim payments by the final date for payment.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of defects which is issued to the integrated supply team. The contract administrator agrees the programme for rectification of items on the schedule of defects with the client and integrated supply team.
The integrated supply team rectifies items listed on the schedules of defects and informs the contract administrator. The contract administrator arranges final inspections of the works and if satisfied issues the certificate of making good defects.
If a site waste management plan has been prepared, the integrated supply team may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
The integrated supply team co-ordinates the preparation of a final report and issues this to the client (or funder).
The client (or funder) and integrated supply team agree the final account. The contract administrator checks the final account and issues the final certificate (payment notice). If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation.
The client (or funder) makes payment by the final date for payment (this will include the release of any remaining retention).
Issuing the final certificate may signify the end of the independent client advisers appointments. If post-occupancy evaluation services are required, these may require a new appointment.
Featured articles and news
A call for prevention and sensitive re-use.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
BSA residential sector competence standards guidance
BSAS 01:2024 Organisational Capability Management System Standard - Competence Assurance.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.