Public project: occupation and defects liability period
The occupation and defects liability period follows practical completion. It is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed (although on some projects, the integrated supply team may go on to operate the development). As the development is now occupied, close co-operation is required between the integrated supply team and the client so as so not to disturb occupants.
Depending on how experienced the client is, they may appoint external consultants to assist them. This means that some of the tasks attributed to the client below might actually be carried out by independent client advisers, a project manager or a contract administrator (employer's agent on design and build projects) and vice versa.
[edit] Starting the work stage.
The integrated supply team arranges a start-up meeting to plan the work stage.
The client may identify a requirement to appoint additional independent client advisers.
[edit] Rectifying defects.
We attribute contract administration tasks (such as making payments under the construction contract) to a contract administrator. Under some forms of procurement (such as design and build) the contract administrator (sometimes referred to as the employer's agent) will work for the client, however, on private finance initiative (PFI) projects, the client will not be a party to the construction contract and will not make payments for construction. Instead, the body funding the integrated supply team (perhaps a special purpose vehicle (SPV)) will take on the role of client for the construction contract and so they may appoint the contract administrator.
If the contract allows, the contract administrator may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the contract administrator (or integrated supply team). On large projects the integrated supply team may set up a hot desk for responding to any complaints or provide assistance required by the incoming occupants. The integrated supply team and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to co-ordinate amendments to the health and safety file.
If any amounts are due to the integrated supply team, they prepare interim applications for payment. The contract administrator checks applications for payment and issues interim certificates (payment notices).The notices must be issued within five days of the dates for payment set out in the contract. If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client (or funder) makes interim payments by the final date for payment.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of defects which is issued to the integrated supply team. The contract administrator agrees the programme for rectification of items on the schedule of defects with the client and integrated supply team.
The integrated supply team rectifies items listed on the schedules of defects and informs the contract administrator. The contract administrator arranges final inspections of the works and if satisfied issues the certificate of making good defects.
If a site waste management plan has been prepared, the integrated supply team may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
The integrated supply team co-ordinates the preparation of a final report and issues this to the client (or funder).
The client (or funder) and integrated supply team agree the final account. The contract administrator checks the final account and issues the final certificate (payment notice). If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation.
The client (or funder) makes payment by the final date for payment (this will include the release of any remaining retention).
Issuing the final certificate may signify the end of the independent client advisers appointments. If post-occupancy evaluation services are required, these may require a new appointment.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February