Prime cost contract
Prime cost contracts (such as JCT PPC 11) are sometimes called cost plus contracts or cost reimbursement contracts.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete.
This method of procurement is not generally recommended, but it can be useful under particular circumstances where an immediate start on site is necessary (for example for urgent alteration or repair work, or if there has been a building failure or a fire, requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Tendering proceeds based on an outline specification, any drawings and an estimate of costs. The contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. The fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
Other basis for payment are possible, including combinations of lump sum and percentage fees. For example, it might be possible to fix some elements of overheads whilst applying a percentage to other elements and to profit.
This is a high risk form of procurement for the client as they are reliant on the contractor working efficiently and procuring sub-contracts economically. Sub contracts may be procured competitively, but there may be little incentive for the contractor to secure or select economic bids. Some of these difficulties can be mitigated if a partnering relationship has been established between the client and the contractor.
NB: Some people consider that a cost reimbursable contract or cost plus contract is one in which the client takes all the risk, whereas a prime cost contract is one in which the cost of the works packages (the prime cost) are reimbursed but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
[edit] Related articles
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments
For small alternation project of 8 storey building, what is the advantage of using prime cost contract?
Unless an immediate start is needed - for example if there is some danger or urgency, it is difficult to see what the advantage would be over a traditional contract.