Precedence diagram method
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘precedence diagram method’, or PDM, refers to:
A method of constructing a logic network using nodes to represent the activities and connecting them by lines that show dependencies.
The Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, suggest that a precedence diagram is a network in which the nodes symbolise activities, also referred to as an 'activity-on-the-node network'.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Gantt chart.
- Information release schedules.
- Milestones.
- Programme consultant.
- Programme float.
- Programme for building design and construction
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
[edit] External references
Featured articles and news
Restoring Alexander Pope's grotto
The only surviving part of his villa in Twickenham.
International Women's Day 8 March, 2025
Accelerating Action for For ALL Women and Girls: Rights. Equality. Empowerment.
Lack of construction careers advice threatens housing targets
CIOB warning on Government plans to accelerate housebuilding and development.
Shelter from the storm in Ukraine
Ukraine’s architects paving the path to recovery.
BSRIA market intelligence division key appointment
Lisa Wiltshire to lead rapidly growing Market Intelligence division.
A blueprint for construction’s sustainability efforts
Practical steps to achieve the United Nations Sustainable Development Goals.
Timber in Construction Roadmap
Ambitious plans from the Government to increase the use of timber in construction.
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Competence framework for sustainability
In the built environment launched by CIC and the Edge.
Institute of Roofing members welcomed into CIOB
IoR members transition to CIOB membership based on individual expertise and qualifications.
Join the Building Safety Linkedin group to stay up-to-date and join the debate.
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.
A brief description and background to this new February law.
Everything you need to know about building conservation and the historic environment.
Comments
Will any one answer me if I post a comment
That depends what the comment is.